API 570 Certification Prep API 578 Practice Questions MSTS 1 February 2013 This following study aid helps you learn the content of API RP-578, Materia...
API 570 Inspector Certification Training Study Suggestions MSTS 2 June 2007 4. MATERIALS The first step in preparing for the exam is to obtain the right codes
Registration for the API 570 Training Course must be received 4 weeks prior to the start of ... End of chapter questions ... (i.e "API ICP 570 Exam Pack"(Sept
• Certification & Exam Information ... • API 653 Above ground Storage Tank API • API 570 Authorized Piping Inspector API ... API 570 PIPIING INSPECTOR
API 510 Inspector Certification Training Study Suggestions MSTS 2 June 2007 4. MATERIALS The first step in preparing for the exam is to obtain the right codes
9.3 Welding documentation reviews: the exam questions 93 9.4 ASME IX article I 95 9.5 ASME IX article II 98 ... Quick Guide API 570 - EBook Created Date:
Api 570 Practice Quiz.pdf ... API 572 Study Guide Practice Questions ... rate on CNL Certification Exam (as of. Related eBooks:
API 571 Certification Preparation ... (above the basic core API 510, 570 & 653examinations) ... • Successfully pass the API RP 571 ICP exam
Certification Training Manual This program is not intended to gauge the technical skills of technicians regarding the diagnosis and repair of motor
“Through Red Hat’s training and certification program, ... We are here to help guide you toward your learning goals. ... RED HAT OPENSTACK ADMINISTRATION II CL210
API 571: Supplemental Inspection Certification Program ... (API Exam Preparation Training) ... (API 510, API 570, API 653) and conducting Risk Based
Architect - Associate. AWS Certified Solutions. Architect - Professional. Available AWS Certifications. Preparing for Your Exam. Hands-on skill and on-the-job experience are the best preparation for an AWS Certification exam. We also highly recommend
CertifiCation training Manual This program is not intended to gauge the technical skills of technicians regarding the diagnosis and repair of motor vehicle air
1 | Page Pre‐test Questions for API 510, 570 & 653 Examinations The API 510, 570 and 653 exams contain 125 scored questions, plus 25 questions
API 570 Note: Exam Window and Deadline dates are Approximate ... 3 MOCK EXAMS with 150 QUESTIONS EACH * Exercises over the API documents and ASME SECTIONS IX and V
Preparation Training for API 570 Exam & Certification ... “trick” questions they will be faced with. ... The API-510 exam date is December 4, 2013
Enterprise Linux Training and Certification ... one-week period ... To learn more about Red Hat certification,
3503 ADAPTING TRAINING PLANS FOR THE PREP DISCUS THROWER by Tommy Badon, Assistant Track Coach, Blinn ColIege, Texas This original offering by Blinn College assistant
The path towards becoming a UAS (or UAV, Drone) pilot begins here. Register today for Geotech’s UAS Flight Training & Remote Pilot Certificate Prep Course
4 UV General Information The API product group represents Full range of spring loaded safety valves acc. to API 526 State-of-the-art design from the safety valve
Tankers operate all over the world to safely deliver petroleum and other hydrocarbons to ports in the United States and beyond, making more than 20,000 calls into
Download gunung tersebut, lereng berbentuk landai. (2) Tipe ... Bentuk Gunung api Kaldera ... d) Tipe Volkano : Kuat, contoh : G. Bromo ,Volkano Lemah : G. Semeru.
ONE (1) WEEK BEFORE YOUR COLONOSCOPY: Stop any iron you are taking, this includes multivitamins with iron. Start following the Low Fiber/Low Residue diet
General Colonoscopy Information COLONOSCOPY A procedure on a clean, prepared colon using a flexible scope with fiber optics to visualize the entire
API 570 Certification Prep API 578 Practice Questions
This following study aid helps you learn the content of API RP-578, Material Verification Program for New and Existing Alloy Piping Systems. There will be about 5 questions from this document on the API 570 exam. We do not spend class time on this publication. So it is important that you become familiar with this content in your personal study sessions. The questions in this study aid are in the same order as API 578. The answer key with references is in the back of this guide. It is helpful to read through API 578 before working on this exercise! Questions in Yellow are Open Book Questions! 1.
API 578 provides guidelines for a material assurance system to verify: a. b. c. d.
2.
The material verification program specified by API 578 covers: a. b. c. d.
3.
only to improve mechanical properties. only to improve corrosion resistance. to improve either mechanical properties or corrosion resistance.
An inspection lot includes: a. b. c. d.
MSTS
only pressure-containing components. only pipe, and fittings. only pipe, fittings, and welds. pressure-containing and non-pressure containing components.
An alloy material is any metallic material that contains alloying elements that are added: a. b. c.
4.
all materials. all alloy materials. only non-ferrous materials. only high-alloy materials.
all materials from a common source. all materials included on the same purchase order. all materials of the same material type (i.e. 316 SS) all materials from a common source, of the same material type and same heat.
1
February 2013
API 570 Certification Prep API 578 Practice Questions
5.
For construction and repair activities a written material verification program should be established by the: a. b. c. d.
6.
The material verification program should cover PMI testing of materials: a. b. c. d.
7.
API 570 Authorized Inspector Owner/User Piping Engineer Repair Organization
During construction the Owner should consider 100% PMI of new components on: a. b. c. d.
Who has the responsibility to determine the extent of PMI performed? a. b. c. d.
9.
during construction of piping systems. in existing piping systems. during repairs and alterations of piping systems. in existing piping systems and during construction, repairs and alterations of piping systems.
During repairs, random PMI sampling of new components is most appropriate for: a. b. c. d. e.
8.
API 570 Authorized Inspector. Engineering Organization. Owner/User. Repair Organization.
all piping systems. all alloys above P-5. exotic alloys. high-risk piping systems.
2
February 2013
API 570 Certification Prep API 578 Practice Questions
10.
Usually substituting an alloy for carbon steel does not cause a problem. But hardenable alloys may cause failure in some carbon steel systems. Which of the following process services would substituting an alloy for carbon steel not result in a potential problem. a. b. c. d.
11.
Who is responsible to assure that the material verification program meets the guidelines of API 578? a. b. c. d.
12.
API 570 Authorized Inspector API 578 Certified Inspector Engineering Organization Owner/User Repair Organization
A mill test report: a. b. c. d.
MSTS
API PMI Specialist Authorized Inspector Piping Engineer Owner/User
Who has the responsibility to review and approve the adequacy of the PMI program used by fabricators? a. b. c. d. e.
eliminates the need for further material verification. is a report showing material discrepancies. is an important part of the material qualify assurance program. is issued by the owner upon receipt of materials. 3
February 2013
API 570 Certification Prep API 578 Practice Questions
15.
During construction, which of the following alloy components does not need to be covered by a material verification program? a. b. c. d. e.
16.
During alloy welding: a. b. c. d.
17.
c. d.
d.
never be used. always receive random PMI testing of weld and base metal. receive random PMI testing of weld and base metal if there is a reason to suspect problems. always receive 100% PMI testing of weld and base metal.
PMI of autogenous welds is: a. b. c. d.
MSTS
is not necessary. is not necessary provided appropriate documentation is provided by the supplier. could be conducted on any of the production welds. could be conducted on a “weld button” prior to production welds.
New longitudinal welded alloyed pipe should: a. b. c.
19.
one electrode from each pallet should be identified. two electrodes from each pallet should be identified. one electrode from each lot or package should be identified. two electrodes from each lot or package should be identified.
If alloy element(s) are contained in the flux of a welding electrode, PMI testing: a. b.
18.
Bolts Expansion Joints Gaskets Pressure containing welds All the above components need to be checked
always required. never required. not required if the weld rod was PMI tested. not required if the base metal was PMI tested.
4
February 2013
API 570 Certification Prep API 578 Practice Questions
20.
Who has the responsibility to determine the extent of PMI testing required on existing piping systems? a. b. c. d.
21.
When prioritizing the need for PMI on existing piping systems, which of the following is not a factor to consider? a. b. c. d. e.
22.
C Cr Cu Fe Ni
Low silicon carbon steel can corrode rapidly when exposed to: a. b. c. d.
MSTS
chrome systems. stainless systems. any ferritic systems. any non-ferrous systems.
Which residual element in a carbon steel system has not caused increased corrosion rates in HF acid piping system? a. b. c. d. e.
24.
Age of the facility Consequence of failure Likelihood of failure Plant experience with inadvertent material substitutions Reason for the alloy
Incorrect substitution of carbon steel is most likely to be found in: a. b. c. d.
23.
API Authorized Inspector Engineering Organization Owner/User Repair Organization
API 570 Certification Prep API 578 Practice Questions
25.
Carbon steel can corrode rapidly in hydrogen-free sulfidation when the silicon content in carbon steel is: a. b. c. d.
26.
A 10’ length of 6 NPS 316L SS pipe 6 NPS Gate valve 4 NPS Monel elbow Slip-on flange
Who has the responsibility to determine the extent of PMI testing required during repairs and alterations of piping systems? a. b. c. d.
MSTS
A 20’ length of 6 NPS pipe Weld-neck flange Expansion joint Bolting
Which of the following piping components is most likely to have a substitution with the wrong material? a. b. c. d.
29.
The effectiveness of the construction & maintenance practices The effectiveness of the inspection practices Age of the unit Line size
Which of the following piping components is most likely to have a substitution with the wrong material? a. b. c. d.
28.
0.10%. 0.10%. 0.25%. 0.25%.
The owner decides to conduct PMI testing on some existing piping systems. Which of the following is a major factor in prioritizing the pipe? a. b. c. d.
27.
< > < >
API 578 Authorized Inspector Engineering Organization Owner/User Repair Organization
6
February 2013
API 570 Certification Prep API 578 Practice Questions
30.
Who has the responsibility to evaluate the effectiveness of a PMI program during repairs and alterations? a. b. c. d. e.
31.
During repairs and alterations the Owner should: a. b. c. d.
32.
when temporarily removing spool pieces. when sending pumps out for repair. by using carbon steel in a 300 series stainless steel system. by using 300 series stainless steel in a carbon steel system.
Identification of materials by visual stamps or markings: a. b. c. d.
MSTS
done by only checking material stampings. accomplished by the Authorized Inspector. not important since materials will be checked during fabrication. not an important part of the material verification program. not a substitute for PMI testing required during fabrication.
In the petrochemical industry, one common material mix-up problem occurs: a. b. c. d.
34.
use NACE certified examiners. have a written procedure describing their PMI program. PMI test 100% of all materials. PMI test 100% of all alloy materials.
PMI testing at the warehouse is: a. b. c. d. e.
33.
API Authorized Inspector Examiner Owner/User Piping Engineer Repair Organization
is not an important part of the material verification program. is not a substitute for PMI testing. is important only on high alloy materials. should only be done by inspectors.
7
February 2013
API 570 Certification Prep API 578 Practice Questions
35.
How do portable X-Ray Fluorescence PMI tools work? a. b. c. d.
36.
PMI tools that use X-Ray fluorescence can not detect: a. b. c. d.
37.
carbon. chrome. iron. molybdenum.
How does Portable Optical Emission Spectrometry determine the elements in a material? a. b. c. d. e.
MSTS
Radiation waves excite the materials and the material emits a different spectrum of radiation that can be analyzed. Radiation waves excite the materials and the material emits a different spectrum of light that can be analyzed. Sound waves excite the materials and the material emits a different spectrum of radiation that can be analyzed. Sound waves excite the materials and the material emits a different spectrum of light that can be analyzed.
An electric arc causes a spectrum of light to be emitted from the tested material. The light is analyzed. An electric arc causes a spectrum of radiation to be emitted from the tested material. The radiation is analyzed. X-rays striking the material cause a spectrum of radiation to be emitted from the tested material. The radiation is analyzed. Specific chemicals deposited on the tested material cause a spectrum of colors to be emitted. The colors are analyzed. The surface is polished and etched. A replication is preformed and is analyzed with a microscope.
8
February 2013
API 570 Certification Prep API 578 Practice Questions
38.
Chemical spot testing: a. b. c. d.
39.
PMI tools that use Resistivity Testing are not always able to sort: a. b. c. d. e. f.
40.
calibrated every 4 hrs. calibrated as specified by the manufacturer. used only by the manufacturer’s personnel. used by owner/user personnel.
All personnel performing PMI tests should be: a. b. c. d.
MSTS
low chromes. high chromes. 300 series stainless steels. 400 series stainless steels. low chromes and 300 series stainless steels. high chromes and 400 series stainless steels.
PMI testing equipment should be: a. b. c. d.
41.
is the fastest PMI technique. provides an accurate way to determine the percentage of the types of metals in the material. uses droplets of acids or caustics that are placed on the component. Different colors indicated different materials. removes a small amount of surface metal that is placed in a filter paper. Small droplets of reagents are used on the sample and different colors indicated different materials.
qualified by national exam. qualified by the owner/user. knowledgeable about the operation of the PMI test equipment. knowledgeable about the operation of the plant where the PMI is conducted.
9
February 2013
API 570 Certification Prep API 578 Practice Questions
42.
Qualifications for personnel performing PMI testing should be submitted and reviewed by: a. b. c. d. e.
43.
When PMI testing indicates that an alloy is outside the range allowed on the material spec, the component can: a. b. c. d.
44.
API 570 Authorized Inspector Engineering Organization Owner/User Repair organization
What is the appropriate action to take when an incorrect material is located during a PMI sampling of an inspection lot? a. b. c. d. e.
MSTS
Cracking due to differential expansion rates Dilution Lack of Fusion Underbead cracking
An alloy weld overlay is applied to carbon steel base metal. Who has the responsibility to establish the minimum alloy requirements of the asdeposited weld metal? a. b. c. d.
46.
never be used. be used if the alloy percentages exceed requirements. be used in low risk piping systems. be used if accepted by the Owner/User following an assessment.
An alloy weld overlay is applied to carbon steel base metal. What will occur? a. b. c. d.
45.
API. ASNT. the Authorized Inspection. the Owner/User. the Piping Engineer.
Inspect 2 more items from the inspection lot. Inspect 50% of the items from the inspection lot. Inspect 100% of the items from the inspection lot. Inspection all items supplied by that manufacturer. A more extensive inspection of the lot should be considered. 10
February 2013
API 570 Certification Prep API 578 Practice Questions
47.
A color code system for pipe is specified by: a. b. c. d.
48.
Identification of materials by color coding: a. b. c. d.
49.
Carbon. Chrome. Oxides. Sulfur.
When PMI testing is conducted on a new piping system, the documentation of the PMI results should be kept: a. b. c. d. e.
MSTS
Whether the marking should remain legible for the component’s life The name of individual doing the marking If colors are used, a description of color used for each alloy
Marking pens should not contain chlorides or: a. b. c. d.
51.
is not an important part of the material verification program. is not a substitute for PMI testing. is important only on high alloy materials. should only be done by inspectors.
Which of the following is not required when the owner’s PMI system requires physical marking of components? a. b. c.
50.
ASME B31.3. ASME 16.34. NACE 3389. PFI ES22.
until the piping system is operational. 1 year. until piping system is no longer in operation. until piping system is removed/scrapped. forever.
11
February 2013
API 570 Certification Prep API 578 Practice Questions