Production, Capacity and Material Planning - univie.ac.at

Production, Capacity and Material Planning. a. ... Control. Updates. ... Capacity Planning `Bottleneck in production facilities...

8 downloads 504 Views 735KB Size
Chapter 7

Production, Capacity and Material Planning

Production, Capacity and Material Planning Production plan quantities of final product, subassemblies, parts needed at distinct points in time To generate the Production plan we need: end-product demand forecasts Master production schedule Master production schedule (MPS) delivery plan for the manufacturing organization exact amounts and delivery timings for each end product accounts for manufacturing constraints and final goods inventory

Production Management

101

Production, Capacity and Material Planning Based on the MPS: rough-cut capacity planning Material requirements planning determines material requirements and timings for each phase of production

detailed capacity planning

Production Management

102

Production, Capacity and Material Planning Updates

Rough-Cut Capacity

End-Item Demand Estimate

Master Production Schedule (MPS)

Detailed Capacity Planning

Material Requirements Planning (MRP)

Material Plan

Purchasing Plan Shop Floor Control

Shop Orders Updates

Production Management

103

Master Production Scheduling Aggregate plan demand estimates for individual end-items demand estimates vs. MPS inventory capacity constraints availability of material production lead time ... Market environments make-to-stock (MTS) make-to-order (MTO) assemble-to-order (ATO)

Production Management

104

Master Production Scheduling MTS produces in batches minimizes customer delivery times at the expense of holding finishedgoods inventory MPS is performed at the end-item level production starts before demand is known precisely small number of end-items, large number of raw-material items MTO no finished-goods inventory customer orders are backlogged MPS is order driven, consisits of firm delivery dates

Production Management

105

Master Production Scheduling ATO large number of end-items are assembled from a relatively small set of standard subassemblies, or modules automobile industry MPS governs production of modules (forecast driven) Final Assembly Schedule (FAS) at the end-item level (order driven) 2 lead times, for consumer orders only FAS lead time relevant

Production Management

106

Master Production Scheduling MPS- SIBUL manufactures phones three desktop models A, B, C one wall telephone D MPS is equal to the demand forecast for each model WEEKLY MPS (= FORECAST) Product Model A Model B Model C Model D weekly total monthly total

1 1000 1500 600 3100

Jan Week 2 3 1000 1000 500 500 1500 1500 600 3000 3600 12200

4 1000 1500 2500

Production Management

5 2000 350 1000 3350

Feb Week 6 7 2000 2000

300 2300 12200

1000 200 3200

8 2000 350 1000 3350

107

Master Production Scheduling MPS Planning - Example MPS plan for model A of the previous example: Make-to-stock environment No safety-stock for end-items ⌧It = It-1 + Qt – max{Ft,Ot} ⌧It = end-item inventory at the end of week t ⌧Qt = manufactured quantity to be completed in week t ⌧Ft = forecast for week t ⌧Ot= customer orders to be delivered in week t INITIAL DATA Model A Current Inventory = 1600 forecast Ft orders Ot

1 1000 1200

Jan Week 2 3 1000 1000 800 300

4 1000 200

Production Management

5 2000 100

Feb Week 6 7 2000 2000

8 2000

108

Master Production Scheduling Batch production: batch size = 2500 ⌧It = max{0, It-1 } – max{Ft, Ot}

⎧0, if I t > 0 Qt = ⎨ ⎩2500, otherwise ⌧I1 = max{0, 1600} – max{1000, 1200} = 400 >0 ⌧I2 = max{0, 400} – max{1000, 800} = -600 <0 => Q2 = 2500 ⌧I2 = 2500 + 400 – max{1000, 800} = 1900, etc. MPS Jan Feb Week Week Current Inventory = 1600 1 2 3 4 5 6 7 forecast Ft 1000 1000 1000 1000 2000 2000 2000 orders Ot 1200 800 300 200 100 Inventory It 1600 400 1900 900 2400 400 900 1400 MPS Qt 2500 2500 2500 2500 ATP 400 1400 2200 2500 2500 Production Management

8 2000 1900 2500 2500 109

Master Production Scheduling Available to Promise (ATP) ⌧ATP1 = 1600 + 0 – 1200 = 400 ⌧ATP2 = 2500 –(800 + 300) = 1400, etc. ⌧Whenever a new order comes in, ATP must be updated

Lot-for-Lot production MPS Current Inventory = 1600 forecast Ft orders Ot Inventory It 1600 MPS Qt ATP

1 1000 1200 400 0 400

Jan Week 2 3 1000 1000 800 300 0 0 600 1000 0 700

4 1000 200 0 1000 800

Production Management

5 2000 100 0 2000 1900

Feb Week 6 7 2000 2000

8 2000

0 2000 2000

0 2000 2000

0 2000 2000

110

Master Production Scheduling MPS Modeling differs between MTS-ATO and MTO find final assembly lot sizes additional complexity because of joint capacity constraints cannot be solved for each product independently

Production Management

111

Master Production Scheduling

Make-To-Stock-Modeling Qit = production quantity of product i in period t Iit = Inventory of product i at end of period t Dit = demand (requirements) for product i in time period t a i = production hours per unit of product i h i = inventory holding cost per unit of product i per time period A i = set-up cost for product i G t = production hours available in period t yit = 1,if set-up for product i occurs in period t (Qit > 0)

Production Management

112

Master Production Scheduling Make-To-Stock-Modeling n

T

min ∑∑ ( Ai yit + hi I it ) i =1 t =1

I i ,t -1 + Qit − I it = Dit n

∑a Q i =1

i

it

≤ Gt

for all (i,t) for all t

T

Qit − yit ∑ Dik ≤ 0

for all (i,t)

k =1

Qit ≥ 0; I it ≥ 0; yit ∈ {0,1} Production Management

113

Master Production Scheduling Assemble-To-Order Modeling two master schedules MPS: forecast-driven FAS: order driven overage costs holding costs for modules and assembled products shortage costs final product assemply based on available modules no explicit but implicit shortage costs for modules final products: lost sales, backorders

Production Management

114

Master Production Scheduling m module types and n product types Qkt = quantity of module k produced in period t gkj = number of modules of type k required to assemble order j

Decision Variables: Ikt = inventory of module k at the end of period t yjt = 1, if order j is assembled and delivered in period t; 0, otherwise hk = holding cost πjt = penalty costs, if order j is satisfied in period t and order j is due in period t’ (t’ t

Production Management

115

Master Production Scheduling Assemble-To-Order Modeling m

L

n

L

min ∑∑ hk I kt + ∑∑ π jt y jt k =1 t =1

j =1 t =1

subject to n

I kt = I k ,t −1 + Qkt − ∑ g kj y jt

for all (k, t)

j =1

n

∑a j =1

j

y jt ≤ Gt

L

∑y t =1

jt

for all t

=1

I kt ≥ 0;

for all j y jt ∈ {0,1} Production Management

for all (j, k, t) 116

Master Production Scheduling Capacity Planning Bottleneck in production facilities Rough-Cut Capacity Planning (RCCP) at MPS level feasibility detailed capacity planning (CRP) at MRP level both RCCP and CRP are only providing information

Production Management

117

Master Production Scheduling MPS: Product A B C D

A B C D

1 1000 1500 600

January Week 2 3 1000 1000 500 500 1500 1500 600

4 1000 1500 -

Bill of capacity (min) Assembly Inspection 20 2 24 2.5 22 2 25 2.4 Capacity requires (hr) Week

1 Assembly Inspection

1133 107

2 1083 104

3 1333!! 128!!

⌧weekly capacity requirements? ⌧Assembly: 1000*20 + 1500*22 + 600*25 = 68000 min = 1133,33 hr ⌧Inspection: 1000*2 + 1500*2 + 600*2,4 = 6440 min = 107,33 hr etc. ⌧available capacity per week is 1200 hr for the assembly work center and 110 hours for the inspection station;

Available capacity 4 per week 883 1200 83 110

Production Management

118

Master Production Scheduling Infinite capacity planning (information providing) finding a feasible cost optimal solution is a NP-hard problem if no detailed bill of capacity is available: capacity planning using overall factors (globale Belastungsfaktoren) required input: MPS standard hours of machines or direct labor required historical data on individual shop workloads (%) Example from Günther/Tempelmeier C133.3: overall factors

Production Management

119

Master Production Scheduling capacity planning using overall factors week 2 80 -

product A B

1 100 40

product A B

work on critical machine 1 4

3 120 60

4 100 -

5 120 40

6 60 -

work on non-critical machine 2 2

Total 3 6

historic capacity requirements on critical machines: 40% on machine a 60% on machine b Production Management

120

Master Production Scheduling in total 500 working units are available per week, 80 on machine a and 120 on machine b; Solution: overall factor = time per unit x historic capacity needs product A: machine a: 1 x 0,4 = 0,4 machine b: 1 x 0,6 = 0,6 product B: machine a: 4 x 0,4 = 1,6 machine b: 4 x 0,6 = 2,4

Production Management

121

Master Production Scheduling capacity requirements: product A machine 1 2 3 a 40 32 48 b 60 48 72 other 200 160 240

week 4 40 60 200

5 48 72 240

6 24 36 120

capacity requirements: product B machine 1 2 3 a 64 96 b 96 144 other 80 120

week 4 -

5 64 96 80

6 -

Production Management

122

Master Production Scheduling

total capacity requirements machine

a b other

1

2

week 3 4

104 156 280

32 48 160

144 216 360

40 60 200

Production Management

5

6

112 168 320

24 36 120

123

capacity requirements

Master Production Scheduling 400 300

a (max 80)

200

b (max 120) other (max 300)

100 0 1

2

3

4

5

6

week

Production Management

124

Master Production Scheduling Capacity Modeling heuristic approach for finite-capacity-planning based on input/output analysis relationship between capacity and lead time G= work center capacity Rt= work released to the center in period t Qt= production (output) from the work center in period t Wt= work in process in period t Ut= queue at the work center measured at the beginning of period t, prior to the release of work Lt= lead time at the work center in period t

Production Management

125

Master Production Scheduling Qt = min{G, U t −1 + Rt } U t = U t −1 + Rt − Qt Wt = U t −1 + Rt = U t + Qt Wt Lt = G

Lead time is not constant assumptions: constant production rate any order released in this period is completed in this period

Production Management

126

Master Production Scheduling Example

0

1 36 20 30

2 36 30 30

Period 3 36 60 36

10

0

0

24

8

12

16

30

30

60

44

48

52

0,83

0,83

1,67

1,22

1,33

1,44

G (hr/week) Rt (hours) Qt (hours) Ut (hours) W t (hours) Lt(weeks)

Production Management

4 36 20 36

5 36 40 36

6 36 40 36

127

Material Requirements Planning Inputs master production schedule inventory status record bill of material (BOM) Outputs planned order releases ⌧purchase orders(supply lead time) ⌧workorders(manufacturing lead time)

Production Management

128

Material Requirements Planning Level 0

End-Item 1 Legend: S/A

Level 1

2

S/A = subassembly

1 Level 2

PP 10 1

2

4

RM = raw material

2 MP 9

Level 4 RM 12

MP = manufactured part

6

S/A

PP 5 4

Level 3

PP = purchased part

part # quantity

RM 13 2

Production Management

129

Material Requirements Planning MRP Process goal is to find net requirements (trigger purchase and work orders) explosion ⌧Example: ⌧MPS, 100 end items ⌧yields gross requirements

netting ⌧Net requirements = Gross requirements - on hand inventory - quantity on order ⌧done at each level prior to further explosion

offsetting ⌧the timing of order release is determined

lotsizing ⌧batch size is determined Production Management

130

Material Requirements Planning Example 7-6

Telephone

Hand Set 11 Assembly

Base 12 Assembly

1

1 Housing S/A

Microphone 111 S/A

1

1 Receiver S/A

1

Tapping Screw

112

115

Hand Set Cord 1

121 Board Pack 122 S/A

Rubber Pad

4

1

2

1 Upper Cover

1

113 Lower Cover

1

123 Tapping Screw

4 114

13

Key Pad

Production Management 1

1211

Key Pad Cord

1

1212 131

124

Material Requirements Planning PART 11 (gross requirements given) net requirements? Planned order release? Net requ.(week 2) = 600 – (1600 + 700) = -1700 =>Net requ.(week2) = 0 Net requ.(week 3) = 1000 – (1700 + 200) = -900 =>Net requ.(week3) = 0 Net requ.(week 4) = 1000 – 900 = 100 etc. current

gross requirements scheduled receipts projected inventory balance net requirements

1200

1

2

3

600

1000

400

700

200

1600

1700

900

week 4

5

6

7

8

1000

2000

2000

2000

2000

0

0

0

0

0

100

2000

2000

2000

2000

planned receipts planned order release

Production Management

132

Material Requirements Planning Assumptions: lot size: 3000 lead time: 2 weeks

current gross requirements scheduled receipts projected inventory balance net requirements planned receipts planned order release

1200

1

2

3

600

1000

400

700

200

1600

1700

900

3000

week 4

5

6

7

8

1000

2000

2000

2000

2000

2900 100 3000

900 2000

1900 2000 3000

2900 2000 3000

900 2000

3000

3000

Production Management

133

Material Requirements Planning Multilevel explosion

part number 12 121 123 1211

description Qty base assembly housing S/A rubber pad key pad

1 1 4 1

lead time is one week lot for lot for parts 121, 123, 1211 part 12: fixed lot size of 3000

Production Management

134

Part 12 gross requirements scheduled receipts projected inventory balance net requirements planned receipts planned order release

current

Part 121 gross requirements scheduled receipts projected inventory balance net requirements planned receipts planned order release

current 0

800

0

1 400 1200 0 0 0

2 600 400 1000 0 0 0

1

2 0

3 1000 400 400 0 0 3000

x1 0

3 3000

4 1000

5 2000

6 2000

7 2000

8 2000

2400 0 3000 0

400 0 0 3000

1400 0 3000 3000

2400 0 3000 0

400 0 0 0

7

8

x1

4 0

5 3000

0 0 0 3000

0 0 3000 3000

x4 500

Part 123 gross requirements scheduled receipts projected inventory balance net requirements planned receipts planned order release

current 0

Part 1211 gross requirements scheduled receipts projected inventory balance net requirements planned receipts planned order release

current 0

15000

1200

500 0 0 0 1

500 0 0 2500

x1 2

0 15000 0 0 0 1 0 1500 2700 0 0 0

0 10000 25000 0 0 0 2 2500 200 0 0 0

0 0 2500 0

x1

x1

x1

6 3000

x4

0 0 3000 0

3 12000

4 0

5 12000

6 12000

13000 0 0 0

13000 0 0 0

1000 0 0 11000

0 0 11000 0

3

5 3000

6

0

4 3000

200 0 0 2800

0 0 2800 3000

0 0 3000 0

Production Management

x4

0

0

0 0 0 0

0 0 0 0

7

8 0

0

0 0 0 0

0 0 0 0

7

8

0

0

0

0 0 0 0

0 0 0 0

0 0 0 0

135

Material Requirements Planning MRP Updating Methods MRP systems operate in a dynamic environment regeneration method: the entire plan is recalculated net change method: recalculates requirements only for those items affected by change Product A B C D

Product A B C D

5 2000 350 1000 -

February Week 6 7 2000 2000 1000 300 200

8 2000 350 1000 -

Updated MPS for February Week 5 6 7 8 2000 2000 2300 1900 500 200 150 1000 800 1000 300 200 -

Net Change for February Week 5 6 7 8 300 -100 150 200 -200 -200

Production Management

136

Material Requirements Planning Additional Netting procedures implosion: ⌧opposite of explosion ⌧finds common item

combining requirements: ⌧process of obtaining the gross requirements of a common item

pegging: ⌧identify the item’s end product ⌧useful when item shortages occur

Production Management

137

Material Requirements Planning Lot Sizing in MRP minimize set-up and holding costs can be formulated as MIP a variety of heuristic approaches are available simplest approach: use independent demand procedures (e.g. EOQ) at every level

Production Management

138

Material Requirements Planning MIP Formulation Indices: i = 1...P t = 1...T m = 1...M

label of each item in BOM (assumed that all labels are sorted with respect to the production level starting from the end-items) period t resource m

Parameters: Γ(i) Γ-1(i) si cij hi ami bmi Lmt ocm G Dit

set of immediate successors of item i set of immediate predeccessors of item i setup cost for item i quantity of itme i required to produce item j holding cost for one unit of item i capacity needed on resource m for one unit of item i capacity needed on resource m for the setup process of item i available capacity of resource m in period t overtime cost of resource m large number, but as small as possible (e.g. sum of demands) external demand of item i in period t Production Management

139

Material Requirements Planning Decision variables: xit Iit Omt yit

deliverd quantity of item i in period t inventory level of item i at the end of period t overtime hours required for machine m in period t binary variable indicating if item i is produced in period t (=1) or not (=0)

Equations:

P T

T M

i =1t =1

t =1m=1

min ∑ ∑ ( si yit + hi I it ) + ∑ ∑ ocmOmt I i ,t = I i ,t −1 + xi ,t − P

∑c

j∈Γ ( i )

ij

x jt − Dit

∑ (ami xit + bmi yit ) ≤ Lmt + Omt

i =1

∀i, t

xit − Gy it ≤ 0 ∀i, t

∀m, t

xit , I it , Omt ≥ 0,

yit ∈ {0,1} ∀ i, m, t

Production Management

140

Material Requirements Planning Multi-Echelon Systems Multi-echelon inventory each level is referred as an echelon “total inventory in the system varies with the number of stocking points” Modell (Freeland 1985): ⌧demand is insensitive to the number of stocking points ⌧demand is normally distributed and divided evenly among the stocking points, ⌧demands at the stocking points are independent of one another ⌧a (Q,R) inventory policy is used ⌧β-Service level (fill rate) is applied ⌧Q is determined from the EOQ formula

Production Management

141

Material Requirements Planning Reorder point in (Q,R) policies: i: total annual inventory costs (%) c: unit costs A: ordering costs τ :lead time σ τ : variance of demand in lead time given a fill rate ∞

β

choose z ( β ) such that:

L ( z ) = ∫ ( y − z ) φ ( y ) dy = z

φ:

(1 − β )Q

στ

density of N(0,1) distribution; L(z): standard loss function Production Management

142

Unit Normal Linear Loss Integral L(Z) Z 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30 2.40 2.50

.00

.02

.04

.3989 .3509 .3069 .2668 .2304 .1978 .1687 .1429 .1202 .1004 .0833 .0686 .0561 .0456 .0367 .0293 .0233 .0183 .0143 .0110 .0084 .0063 .0047 .0036 .0027 .0021

.3890 .3793 .3418 .3329 .2986 .2904 .2592 .2518 .2236 .2170 .1917 .1857 .1633 .1580 .1381 .1335 .1160 .1120 .0968 .0933 .0802 .0772 .0660 .0634 .0539 .0517 .0437 .0418 .0351 .0336 .0280 .0268 .0222 .0212 .0174 .0166 0..0136 .0129 .0104 .0099 .0080 .0075 .0060 .0056 .0044 .0042 .0034 .0032 .0026 .0024 .0018 .0017 Production Management

.06

.08

.3697 .3240 .2824 .2445 .2104 .1799 .1528 .1289 .1080 .0899 .0742 .0609 .0496 .0401 .0321 .0256 .0202 .0158 .0122 .0094 .0071 .0053 .0039 .0030 .0023 .0016

.3602 .3154 .2745 .2374 .2040 .1742 .1478 .1245 .1042 .0866 .0714 .0585 .0475 .0383 .0307 .0244 .0192 .0150 .0116 .0089 .0067 .0050 .0037 .0028 .0022 .0016

143

Material Requirements Planning s = z ⋅σ τ

Safety stock: Reorder point:

R = Dτ + z ⋅ σ τ

Order quantity:

Q = EOQ

=

2AD ic

Average inventory: I (1) = Q + s 2 I ( n ) = average inventory

I (1) =

1 2

for n stocking

points

2A D + zσ τ ic

Production Management

144

Material Requirements Planning

for two stocking points : demand at each point : D/2 variance of lead - time demand : σ τ2 / 2 standard deviation is : σ τ / 2 average inventory at each stocking point is : 1 2AD/2 zσ τ 1 + = (Q / 2 + s ) 2 ic 2 2

Production Management

145

Material Requirements Planning

the average inventory for two stocking point is : ⎡ 1 ⎤ I (2) = 2 ⎢ (Q / 2 + s )⎥ = 2 (Q / 2 + s ) = 2 ⋅ I (1) ⎦ ⎣ 2 I (n) = n ⋅I (1) for each level the safety stock is : s/ n the total safety stock is n ⋅s

Production Management

146

Material Requirements Planning Example: At the packaging department of a sugar refinery: A very-high-grade powdered sugar: Boxed Sugar

Level 0

Level 1

Sugar

Cartons

Sugar-refining lead time is five days; Production lead time (filling time) is negligible; Annual demand: D = 800 tons and σ= 2,5 Lead-time demand is normally distributed with Dτ = 16 tons and στ = 3,54 tons Fill rate = 95% A = $50, c = $4000, i = 20% Production Management

147

Material Requirements Planning Inventory at level 0 and 1? Safety stock?

2 AD = ic

Q =

2 x 50 x 800 = 10 tons 800

ß = 0,95 => z = 0,71 s = zστ = 0,71x3,54 = 2,51 tons Suppose we keep inventory in level 0 only, i.e., n = 1:

I (1) =

Q 10 +s= + 2,51 = 7 ,51tons 2 2

Suppose inventory is maintained at both level 0 and level 1, i.e., n = 2:

I (2) =

2 I (1) = 10 , 62 tons

The safety stock in each level is going to be:

s 2,51 = = 1,77tons 2 2 Production Management

148

Material Requirements Planning MRP as Multi-Echelon Inventory Control continuous-review type policy (Q,R) hierarchy of stocking points (installation) installation stock policy echelon stock (policy): installation inventory position plus all downstream stock MRP: ⌧rolling horizon ⌧level by level approach ⌧bases ordering decisions on projected future installation inventory level

Production Management

149

Material Requirements Planning ⌧All demands and orders occur at the beginning of the time period ⌧orders are initiated immediately after the demands, first for the final items and then successively for the components ⌧all demands and orders are for an integer number of units ⌧T= planning horizon ⌧τi= lead time for item i ⌧si= safety stock for item I ⌧Ri= reorder point for item I ⌧Qi=Fixed order quantity of item i ⌧Dit= external requirements of item i in period t

Production Management

150

Material Requirements Planning Installation stock policies (Q,Ri) for MRP: a production order is triggered if the installation stock minus safety stock is insufficient to cover the requirements over the next τi periods an order may consist of more than one order quantity Q if lead time τi = 0, the MRP is equal to an installation stock policy. safety stock = reorder point

Production Management

151

Material Requirements Planning Echelon stock policies (Q,Re) for MRP: Consider a serial assembly system Installation 1 is the downstream installation (final product) the output of installation i is the input when producing one unit of item i-1 at the immediate downstream installation wi = installation inventory position at installation i Ii = echelon inventory position at installation i (at the same moment) Ii = wi+ wi-1+... w1 a multi-echelon (Q,R) policy is denoted by (Qi,Rie) Rie gives the reorder point for echelon inventory at i

Production Management

152

Material Requirements Planning R1e = s1+Dτ1 Rie = si+Dτi+Ri-1e +Qi-1 Example: Two-level system, 6 periods

I 10 = 18 , I 20 = 38 , R 1e = 20 , R 2e = 34 , Q 1 = 10 , Q 2 = 30

D = 2 (Item 1), τ1 = 1, τ2 = 2

Production Management

153

Material Requirements Planning

Item 1 Item 2

Period Demand Level w1 Production Level w2 Production

1 2 18 10 10 0

2 2 26 0 10 0

3 2 24 0 10 30

Suppose now that five units were demanded in period 2: Period 2 3 4 5 Demand 5 2 2 2 Level w1 23 21 19 27 Item 1 Production 0 0 10 0 Level w2 10 10 30 30 Item 2 Production 30 0 0 0

4 2 22 0 10 0

5 2 20 10 30 0

6 2 25 10 30 0

Production Management

6 2 28 0 10 0

7 2 23 0 30 0

154

Material Requirements Planning Lot Size and Lead Time lead time is affected by capacity constraints lot size affects lead time batching effect an increase in lot size should increase lead time saturation effect when lot size decreases, and set-up is not reduced, lead time will increase expected lead time can be calculated using models from queueing theory (M/G/1)

Production Management

155

Material Requirements Planning

L = lead time (λ / μ ) 2 + λ2σ 2 1 + L= 2λ (1 − λ / μ ) μ

λ = mean arrival rate μ = mean service rate σ 2 = service time variance Production Management

156

Material Requirements Planning D j = demand per period for product t j = unit - production

j

time for product

S j = set - up time for product Q j = lotsize for product

j

j

j

mean arrival rate of batches : n n D λ = ∑ λj = ∑ j j =1 j =1 Q j mean service time : n

1

μ

=

∑λ j =1

( S j + t jQ j ) j n

∑λ j=1

service - time variance : n

σ

2

=

∑λ j =1

j

j

( S j + t jQ j ) 2 n

∑λ j =1

Production Management

j

⎛ 1 ⎞ − ⎜⎜ ⎟⎟ ⎝μ ⎠

2

157

Material Requirements Planning

Production Management

158

Material Planning Work to do: 7.7ab, 7.8, 7.10, 7.11, 7.14 (additional information: available hours: 225 (Paint), 130 (Mast), 100 (Rope)), 7.15, 7.16, 7.17, 7.31-7.34

Production Management

159