Why is Practical Completion Important - CICES

1 Tim Hallworth, Associate Lighthouse Club Seminar on Contract Management "Complete or Not Complete, That is the Question" 19 June 2010 www.hoganlovel...

7 downloads 734 Views 57KB Size
Why is Practical Completion Important ? Lighthouse Club Seminar on Contract Management

For Contractors

"Complete or Not Complete, That is the Question"

No longer liable for Liquidated Damages

19 June 2010

Half retention becomes due

Tim Hallworth, Associate

Defect Liability Period commences Insurance risks ends For Employers Period for finalisation and agreement of Final Account starts Possession and occupation starts www.hoganlovells.com

What is Practical Completion ? –Text Books

Hong Kong "Building" Standard Forms (1) Hong Kong Standard Form of Building Contract Private Edition – With Quantities 2005 Edition

Hudson's

'The state of completion where the Works... may not be absolutely completed or entirely free from defects but have reached the state where they can be taken over and used by the Employer for their intended purpose and where the unfinished items of work and the remaining defects then patent are only of a minor nature and extent and their completion or rectification will not unreasonably interfere with or interrupt the taking over of the Works...'

"Usually it (completion) will mean bona fide completion free of known or patent defects so as to enable the owner to enter into occupation". -

2

The words 'practical' or 'substantial' in English standard forms probably do no more than indicate that trivial defects not affecting beneficial occupancy will not prevent completion..."

-

Wording is less stringent than the Hudson's definition: - Most prescriptive definition - Can have patent defects but of a minor nature ! - Whether defects are patent or minor defects will be a matter of fact - Discretion is left to the certifier

www.hoganlovells.com

3

www.hoganlovells.com

Hong Kong "Building" Standard Forms (2)

Hong Kong "Civil" Standard Form





Government of Hong Kong General Conditions of Contract for Building Works 1993 Edition

• • •

No prescriptive definition as the new form ! Often tests are not defined in the Specification More at the discretion of the Architect

www.hoganlovells.com

5

Hong Kong Conditions of Contract for Civil Engineering Construction Contract 1977 Edition Clause 68. "As soon as in the opinion of the Engineer the Works shall have been substantially completed and shall have satisfactorily passed any final test which may be prescribed by the Contract, the Engineer, on receiving a written undertaking by the Contractor ..., shall issue a certificate of completion in respect of the Works."

Clause 53. (1) "When the Works have been substantially completed and have satisfactorily passed any final test that may be prescribed by the Contract..." Clause 53. (2) ... as soon as in the opinion of the Architect the Works have been substantially completed and satisfactorily passed any final test which may be prescribed by the Contract, the Architect shall issue a certificate of completion in respect of the Works"

4

• • • • •

Similar to Building Works 1993 Edition No prescriptive definition Refers to final tests At the opinion of the Engineer Contractor makes application that the works are Practically Complete

www.hoganlovells.com

6

1

English Authorities (1)

Other Standard Forms – No use of the term PC/SC !

J. Jarvis and Sons -v- Westminster Corporation (1978) 7 BLR 64 HL

NEC3 Engineering and Construction Contract June 2005 Edition. Defines 'Completion' as being:

-

Brief facts: Works delayed by a nominated piling contractor (defective piles)

(i) done all the work which the Works Information states he is to do by the Completion Date; and

-

(ii) corrected notified Defects which would have prevented the Employer from using the works and Others from doing their work.

practical completion as completion for the purpose of allowing the employers to take possession of the works and use them as intended.

-

practical completion did not mean completion down to the last detail, however trivial and unimportant.

-

Only latent defects at the date of practical completion

-

High standard !

When the Contractor has:

FIDIC 1999 Form Completion is defined by tests and the completion of specified work and the issuance of a Taking Over Certificate. www.hoganlovells.com

7

English Authorities (2)

Emson Eastern Ltd -v- E.M.E. Developments Ltd (1991) 55 BLR114

-

Brief facts: Contract for site preparation defective drains

-

practical completion did not mean that very minor (de minimus work) had to be carried out, but did mean that if there were any patent defects the Architect should not give a certificate of practical completion. Free from patent obvious defects

-

Diluted the strict interpretation of Jarvis !

www.hoganlovells.com

9

Hong Kong Cases (2)

-

Brief facts: PC certified after Emson went into receivership. Issues was if all snagging and remedial works were required to be made good before completion

-

Realistic definition of practical completion !

-

"should keep in mind that building construction is not like the manufacture of goods in a factory. ...[it was] impossible to achieve the same degree of perfection as can a manufacturer. His view was that it must be rare for a new building to have every screw and every brush of paint correct "

www.hoganlovells.com

10

Mariner - The Arguments

Mariner International Hotels Ltd v Atlas Ltd (2007) HKCFA Agreement signed for sale of hotel in Tsuen Wan 1998 (now serviced apartments) - "Turnkey basis" equivalent to the Grand Plaza Hotel - Completion of sale was conditional upon: - (1) Practical completion of hotel - (2) Occupation Permit for the hotel - (3) Licence for the Hotel to operate - Architect issued PC certificates - Mariner refused to complete the purchase and alleged the conditions had not been satisfied - Atlas accepted that some defects were non-trifling www.hoganlovells.com

8

English Authorities (3)

H.W. Neville (Sunblest) Ltd -v- William Press and Son Ltd (1981) 20 BLR 78

-

www.hoganlovells.com

11

-

Mariner argued that PC in the building contract sense was not achieved as there were still patent defects which were not trifling ones

-

Atlas argued the hotel was open for business and rectification works were still proceeding (PC in the Big Island sense)

-

Lower court decisions were: -

PC as certificates were issued (Atlas winner at CFI)

-

PC achieved if capable of being opened for business (Atlas winner at CA)

www.hoganlovells.com

12

2

Mariner - What does this mean to Architects and Engineers ??

Mariner - Court of Final Appeal

-

Atlas lost (PC was based on Mariners interpretation and the Hotel was NOT free from patent defects)

-

The parties intended to mean PC in the building contract sense (turnkey contract)

-

Ready for business not enough in the present case

www.hoganlovells.com

13

-

exacting standard: no patent defects except trifling ones

-

The issue is that this definition has fundamentally switched what previously people thought was the issue around PC, namely beneficial use of occupation

www.hoganlovells.com

14

Vigour Ltd v Hyundai Engineering and Construction (August 2008) HKCFI

Vigour - Arbitrator decided

-

Application for leave to appeal against an award

-

-

Definition of PC:

"occupants" means "whoever is likely to occupy a particular part of the hotel" following completion

-

Hyundai did not contract to build an operational hotel

-

Direct contractors carried out follow on works (fitting out etc)

-

"occupants" not necessarily hotel guests and staff

"'Practical Completion' means ... the Works ... fully available for possession and use, subject only to items of minor works ... 'minor works' shall not include work which would otherwise inconvenience or unreasonably disturb occupants in their possession and use of the Works following Practical Completion."

www.hoganlovells.com

e.g. plant rooms: maintenance staff cafe: fitting-out contractor

15

www.hoganlovells.com

16

Vigour - Appeal - Court of First Instance

Contract Management – Practical points

Court agreed with interpretation of Arbitrator:

1. The discretion of the Architect/Engineer as to PC should be exercised with caution;

1. Interpretation sensible where other contractors involved;

2. Works must be almost (if not entirely) finished !

2. More consistent with "use and possession" of any given area; and

3. Try to obtain acknowledgement of the items of work left incomplete;

3. Nothing wrong with varying levels of tolerance.

4. Should be satisfied that the retention money will cover the cost of the remedial works; 5. If an Employer takes possession the Architect should state in writing to the Contractor that he reserves his rights that works are not practically complete (may be difficult!); 6. Should be satisfied there is no likelihood of the Employer suffering loss/interference with the use of the works while items are completed;

www.hoganlovells.com

17

www.hoganlovells.com

18

3

Contract Management – still need of clarity ! 1. Is not relevant as the HK standard forms talk about "Substantial Completion" (rather than Practical Completion) ? 2. Completion definition may vary between the contract forms – HK forms (private and public), NEC and FIDIC forms; 3. If the Employer has occupied then withholding PC is a risky strategy; 4. If outstanding work is trifling (minor) then it will be a risky strategy to withhold PC; (this will be a matter of fact). “de minimus” principle – the law does not concern itself with trifles…

The End

Tim Hallworth, Associate [email protected]

www.hoganlovells.com

19

www.hoganlovells.com

20

www.hoganlovells.com Hogan Lovells has offices in: Abu Dhabi Alicante Amsterdam Baltimore Beijing Berlin Boulder Brussels Budapest*

Caracas Chicago Colorado Springs Denver Dubai Dusseldorf Frankfurt Hamburg Hanoi

Ho Chi Minh City Hong Kong Houston Jeddah* London Los Angeles Madrid Miami Milan

Moscow Munich New York Northern Virginia Paris Philadelphia Prague Riyadh* Rome

San Francisco Shanghai Silicon Valley Singapore Tokyo Warsaw Washington DC Zagreb*

"Hogan Lovells" or the "firm" refers to the international legal practice comprising Hogan Lovells International LLP, Hogan Lovells US LLP, Hogan Lovells Worldwide Group (a Swiss Verein), and their affiliated businesses, each of which is a separate legal entity. Hogan Lovells International LLP is a limited liability partnership registered in England and Wales with registered number OC323639. Registered office and principal place of business: Atlantic House, Holborn Viaduct, London EC1A 2FG. Hogan Lovells US LLP is a limited liability partnership registered in the District of Columbia. The word "partner" is used to refer to a member of Hogan Lovells International LLP or a partner of Hogan Lovells US LLP, or an employee or consultant with equivalent standing and qualifications, and to a partner, member, employee or consultant in any of their affiliated businesses who has equivalent standing. Rankings and quotes from legal directories and other sources may refer to the former firms of Hogan & Hartson LLP and Lovells LLP. Where case studies are included, results achieved do not guarantee similar outcomes for other clients. New York State Notice: Attorney Advertising. © Copyright Hogan Lovells 2010. All rights reserved. * Associated offices

4