Case Study Project Management and Project Planning Decommissioning Project Greifswald Axel Bäcker
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents
project strategy/planning
project implementation
project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)
project analysis
key decisions
licensing strategy/project planning
project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Basic tasks and objectives investigation of scenarios for the company strategy timely sequence of main tasks planning of the necessary personnel (qualification measures) evalution of alternatives (technical, personnel)
ã definition of the company strategy (decommissioning main goals)
ã WBS creation (part projects definition)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Steps system analysis à
definition of the overall strategy
detailed analysis for main issues à
technical strategy
à
personnel development
à
cost development
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis Main considerations • • • • • •
(fuel management) Material (waste) management & mass flow logistic dismantling strategy post operation personnel strategy site reuse options
define main dependencies between activities define mile stones and overall project life time prepare key decision plan (with arguments) HOW to do it??
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis Practical realisation
Basis for the decision making process (system analysis)
DECISION TREE
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis Decision tree dismantling
Energiewerke Nord Energiewerke NordGmbH GmbH Unternehmensentwicklung Stillegung und Abbau
1990
ja
Unternehmensentwicklung integrierte Standortentwicklung
1990
nein
1
Personalstrategie AR-Beschluß 1990 sicherer Einschluß nein
Ende
ja
2
Unterstützung Region, aktive Öffentlichkeitsarbeit
1991
Flächenrecycling und Demontage Altanlagen
nein
3
1991
Stillegungskonzeptstudie EWN, KAH, NIS Ende
ja ABBAU BRENNELEMENTE
STILLEGUNGSABFÄLLE
BETRIEBSABFÄLLE
STANDORTBETRIEB
NACHBETRIEB
32
nein
Industriebrache
ja
1992
defekte Brennelemente
aus freien Marktgründen nur teilweise realisiert
feste Abfälle
ja
ja
nein
33
nein
Einlagerung Morsleben
1993
10
7
25
Konditionierung mobile Anlage
Konditionierung ZLN
ja
nein
ja nein
ja
ja
14
16
nein
aus Wirtschaftlichkeitsbetrachtungen aufgegeben
nein
Ende
nein
Ende Bereitstellung Sonderbehälter und Handhabungstechnik
1995
Konfektionierung vor Ort oder ZLN Ende
Schmelzanlage/ Verdampferanlage EWN nein
15
nein
5
ZLN
Schmelzanlage Extern/ Verdampferanlage ZLN Ende
Ende
ja
nein
28
Ende
nein Personalausstellung
ja
nein
29
nein
Restbetrieb
ja Abbau mit Fremdunternehmen
19
nein
ZLN
24
nur Halle 7
ja
ja
Ende
nein
ja
37
1994
39
Personalausstellung
ja
nein Personalausstellung Ende
Personaltransfer zu Stillegung und Abbau
ja (EWN)
38
1995
nein (§ 249 h)
ja
Realisierung Infrastruktur für Investorprojekte
Personalausstellung Ende
Ende
21
Block 5, KKR-MH geklärt
22
1996
abhängig von Realisierung TTC und Privatisierungs-/ Industrialisierungskonzepten
nein
Personalumsetzung möglich bis Bereitstellung Abbautechnik
Ende Entwicklung Technik Castor/Pollux
36
Ende
ja
Ende
nein
Personaltransfer zu Stillegung und Abbau
Ende
Abbautechniken verfügbar
Ende
Umlagerung Castor ZLN
ja
35
Personalausstellung
Terminverzug 1:1
nein
20
Beräumung unterirdische Wirtschaft
Ende
30
Ende
1993 nein
Ende
Personalzuordnung zum Stellenplan Stillegung und Abbau
ja
stationäre Anlage Zustandsanalyse konform Erwartungen
34
Personaltransfer zu Stillegung und Abbau
Ende
nein
Ende
Anpassung Infrastruktur für Investorprojekte
ja
23
ja
Rekultivierung
Erschließung der Flächen für Neuanlagen
Qualifikation vorhanden ja
ja
nein Ende
KRB-MOX
1997
nein
26
Nachqualifizierung
Personaltransfer zu Stillegung und Abbau
Stillegungsgenehmigung
1996 Castor ZLN
Umlagerung des Personals bei Ausgliederung
ja
ja
ja ja
ja
nein
nein
27
Ausgliederung nach § 613 a BGB
nein
18
keine Rückstellung für KGR, KKR Gebäudeabriß
8 Ende
Modellprojekt Block 5-8 Teilstillegungsvorhaben
nein
Konfektionierung ZAW
ja 11
ja
ja 13
Bereitstellung VERA + weitere Lagerkapazität
Castor Block 1-5 bzw. Rheinsberg
nein
Einsatz und Auswahl EWN-Stammpersonal für Stillegung und Abbau ja
nein
Ende
1994
yes 17
Einlagerung ZAB nein
Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von Betriebseinheiten
complete dismantling no
ja
6 nein
1992
nein 12
4 Transporttechnik für Einlagerung verfügbar
Ende
Entwicklung zum Energie- und Industriestandort
nein
1997
Personalausstellung Ende
Personaleinsatz außerhalb EWN ja
1998
31
BE-Wiederaufarbeitung ja
9
nein
nein
Aufbau Stillegungs- und Standortbetreibergesellschaft
schrittweise Personalausstellung
Ende
Endlager
Endlager
Erhaltung Reststruktur
Privatisierung
Ende
Ende
Ende
Ende
1998 Referenzstrategie Strategiealternativen
Ende
Direkte Endlagerung Ende
programm-, personal- und terminbestimmende Meilensteine
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis Decision tree waste management
Energiewerke Nord Energiewerke NordGmbH GmbH Unternehmensentwicklung Stillegung und Abbau
1990
ja
Unternehmensentwicklung integrierte Standortentwicklung
1990
nein
1
Personalstrategie AR-Beschluß 1990 sicherer Einschluß nein
Ende
ja
2
Unterstützung Region, aktive Öffentlichkeitsarbeit
1991
Flächenrecycling und Demontage Altanlagen
nein
3
1991
Stillegungskonzeptstudie EWN, KAH, NIS Ende
ja ABBAU BRENNELEMENTE
STILLEGUNGSABFÄLLE
BETRIEBSABFÄLLE
STANDORTBETRIEB
NACHBETRIEB
32
nein
Industriebrache
ja
1992
defekte Brennelemente
aus freien Marktgründen nur teilweise realisiert
feste Abfälle
ja
ja
nein
33
nein
Disposal Morsleben
1993
10
ja
ja
14
16
nein nein
aus Wirtschaftlichkeitsbetrachtungen aufgegeben
nein
Ende
nein
Ende Bereitstellung Sonderbehälter und Handhabungstechnik
1995
Konfektionierung vor Ort oder ZLN Ende
Schmelzanlage/ Verdampferanlage EWN nein
15
nein
5
ZLN
Schmelzanlage Extern/ Verdampferanlage ZLN Ende
Ende
ja
nein
28
Ende
nein Personalausstellung
ja
nein
29
nein
Restbetrieb
ja Abbau mit Fremdunternehmen
19
nein
ZLN
24
nur Halle 7
ja
ja
Ende
nein
ja
37
1994
39
Personalausstellung
ja
nein Personalausstellung Ende
Personaltransfer zu Stillegung und Abbau
ja (EWN)
38
1995
nein (§ 249 h)
ja
Realisierung Infrastruktur für Investorprojekte
Personalausstellung Ende
Ende
21
Block 5, KKR-MH geklärt
22
1996
abhängig von Realisierung TTC und Privatisierungs-/ Industrialisierungskonzepten
nein
Personalumsetzung möglich bis Bereitstellung Abbautechnik
Ende Entwicklung Technik Castor/Pollux
36
Ende
ja
Ende
nein
Personaltransfer zu Stillegung und Abbau
Ende
Abbautechniken verfügbar
Ende
Umlagerung Castor ZLN
ja
35
Personalausstellung
Terminverzug 1:1
nein
20
Beräumung unterirdische Wirtschaft
Ende
30
Ende
1993 nein
Ende
Personalzuordnung zum Stellenplan Stillegung und Abbau
ja
stationäre Anlage Zustandsanalyse konform Erwartungen
34
Personaltransfer zu Stillegung und Abbau
Ende
nein
Ende
Anpassung Infrastruktur für Investorprojekte
ja
23
ja
Rekultivierung
Erschließung der Flächen für Neuanlagen
Qualifikation vorhanden ja
ja
nein Ende
KRB-MOX
1997
nein
26
Nachqualifizierung
Personaltransfer zu Stillegung und Abbau
Stillegungsgenehmigung
1996 Castor ZLN
Umlagerung des Personals bei Ausgliederung
ja
ja
ja ja
ja
nein
nein
27
Ausgliederung nach § 613 a BGB
nein
18
keine Rückstellung für KGR, KKR Gebäudeabriß
8 Ende
Modellprojekt Block 5-8 Teilstillegungsvorhaben
nein
Konfektionierung ZAW
ja 11
ja
ja 13
Additional storages
Castor Block 1-5 bzw. Rheinsberg
nein
25
Konditionierung mobile Anlage
Konditionierung ZLN nein
Einsatz und Auswahl EWN-Stammpersonal für Stillegung und Abbau ja
ja stop
1994
17
no
yes 7
aus Rückstellungsgründen nur teilweise realisiert
ja
nein
Einlagerung ZAB nein
Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von Betriebseinheiten
kompletter Rückbau
ja
6 nein
1992
nein 12
4 Transporttechnik für Einlagerung verfügbar
Ende
Entwicklung zum Energie- und Industriestandort
nein
1997
Personalausstellung Ende
Personaleinsatz außerhalb EWN ja
1998
31
BE-Wiederaufarbeitung ja
9
nein
nein
Aufbau Stillegungs- und Standortbetreibergesellschaft
schrittweise Personalausstellung
Ende
Endlager
Endlager
Erhaltung Reststruktur
Privatisierung
Ende
Ende
Ende
Ende
1998 Referenzstrategie Strategiealternativen
Ende
Direkte Endlagerung Ende
programm-, personal- und terminbestimmende Meilensteine
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis Overall decision tree EWN
Energiewerke Nord GmbH Unternehmensentwicklung Stillegung und Abbau
1990
ja
Site reuse
1990
nein
1
Personnel strategy AR-Beschluß 1990 sicherer Einschluß nein
Ende
ja
2
Unterstützung Region, aktive Öffentlichkeitsarbeit
1991
Flächenrecycling und Demontage Altanlagen
nein
3
Ende
ja
Fuel elements
Dismantling material
Operational waste
1991
Stillegungskonzeptstudie EWN, KAH, NIS
Dismantling
STANDORTBETRIEB
Post operation
32
nein
Industriebrache
ja
1992
defekte Brennelemente
aus freien Marktgründen nur teilweise realisiert
feste Abfälle
ja
ja
nein
33
nein
Einlagerung Morsleben nein
nein
10
Einlagerung ZAB 7
nein
ja
ja
14
16
aus Wirtschaftlichkeitsbetrachtungen aufgegeben
Ende
Ende
nein
keine Rückstellung für KGR, KKR Gebäudeabriß
nein
Ende Bereitstellung Sonderbehälter und Handhabungstechnik
Modellprojekt Block 5-8 Teilstillegungsvorhaben
Konfektionierung vor Ort oder ZLN Ende
Schmelzanlage/ Verdampferanlage EWN nein
15
nein
ZLN
5
Schmelzanlage Extern/ Verdampferanlage ZLN Ende
Ende
ZLN
nur Halle 7
ja
nein
28
nein
29
nein
ja
nein Personalausstellung
Restbetrieb
ja Abbau mit Fremdunternehmen
nein
24
ja
ja
Umlagerung Castor ZLN
Ende
21
ja
nein Personalausstellung Ende
Personaltransfer zu Stillegung und Abbau
ja (EWN)
38
1995
nein (§ 249 h)
ja
Realisierung Infrastruktur für Investorprojekte
Personalausstellung Ende
Ende
Block 5, KKR-MH geklärt
22
1996
abhängig von Realisierung TTC und Privatisierungs-/ Industrialisierungskonzepten
nein
Personalumsetzung möglich bis Bereitstellung Abbautechnik
Ende Entwicklung Technik Castor/Pollux
39
Personalausstellung
Ende
ja
Ende
1994
Ende
Abbautechniken verfügbar
Ende
nein
Personalausstellung
Terminverzug 1:1
nein
20
36
ja
37
Personaltransfer zu Stillegung und Abbau
Ende
30 Zustandsanalyse konform Erwartungen
Beräumung unterirdische Wirtschaft
nein
Ende
Personalzuordnung zum Stellenplan Stillegung und Abbau
ja
1993 nein
ja
35
Personaltransfer zu Stillegung und Abbau
Ende
nein
19
34
Anpassung Infrastruktur für Investorprojekte
Nachqualifizierung ja
stationäre Anlage Ende
Ende
Erschließung der Flächen für Neuanlagen
Qualifikation vorhanden ja
ja
nein Ende
KRB-MOX
1997
nein
26
Ende
23
ja
Stillegungsgenehmigung
1996 Castor ZLN
ja
Rekultivierung
nein
27
ja
ja ja
ja
Umlagerung des Personals bei Ausgliederung
Ausgliederung nach § 613 a BGB Personaltransfer zu Stillegung und Abbau
nein
18
8
1995
25 nein
nein
nein
Konfektionierung ZAW
ja
11
ja
nein
ja 13
Bereitstellung VERA + weitere Lagerkapazität
Castor Block 1-5 bzw. Rheinsberg
1994
Konditionierung mobile Anlage
Konditionierung ZLN
ja
aus Rückstellungsgründen nur teilweise realisiert
ja Ende
Einsatz und Auswahl EWN-Stammpersonal für Stillegung und Abbau
nein
ja
17
nein
ja nein
Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von Betriebseinheiten
kompletter Rückbau
ja
6
1993
1992
nein 12
4 Transporttechnik für Einlagerung verfügbar
Ende
Entwicklung zum Energie- und Industriestandort
nein
1997
Personalausstellung Ende
Personaleinsatz außerhalb EWN ja
1998
31
BE-Wiederaufarbeitung ja
9
nein
nein
Aufbau Stillegungs- und Standortbetreibergesellschaft
schrittweise Personalausstellung
Ende
Endlager
Endlager
Erhaltung Reststruktur
Privatisierung
Ende
Ende
Ende
Ende
1998 Referenzstrategie Strategiealternativen
Ende
Direkte Endlagerung Ende
programm-, personal- und terminbestimmende Meilensteine
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)
project analysis
key decisions
licensing strategy/project planning
project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning – EWN initial key decisions
Direct dismantling no Safe Enclosure
Introduce project organization Project realisation by own staff instead of contractors Erect major interim store on-site for fuel, waste and treatment Reuse of site for industrial and energetic uses
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)
project analysis
key decisions
licensing strategy/project planning
project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Licensing strategy/project planning -step by step procedure basic documents for dismantling project p a r t o f
o v e r a l l
license 1995
application for dismantling license
issue of dismantling license
pre checking documents
Explanatory reports on - fire protection - dismantling - radiation protection - remote dismantling - waste management Operation manual - procedures of operation systems - radiaton protection ordinance - decommissioning and dismantling ordinance Technical planning: - which parts should be dismantled - which parts should be remained Authority of the country Mecklenburg-Vorpommern
Authorised expert (technical control organisation, experts of fire protection, site safety )
VPU 0 VPU 1
VPU 2
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)
project analysis
key decisions
licensing strategy/project planning
project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Technical concept - contents
main decommissioning and dismantling steps
dismantling principles operational waste management categorisation of systems/buildings/areas by radiological classes inventorisation
mass flow logistic (from dismantling) main items of necessary plant adaptations main items of investments (new equipment, new installations) special dismantling and disposal concept for highly activated components safe post operation, evaluation of the residual life time of old equipment possibilities to reduce costs (alternatives)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Technical concept – dismantling principles
dismantling planning on system basic, execution on room basis
start in unit 5; low contamination / radiation dose
from low to high contamination / radiation dose
use market equipment
in situ decontamination only for dose reduction
whole components / parts as possible for decay or treatment in interim storage
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Technical concept – material categorisation Radiological classes
category I
unrestricted material from the monitored area which is not subject to the release measurement procedure
category II
suspected material (an eventual contamination cannot be excluded) from the monitored area, mainly from the turbine hall
category III
contaminated material
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Technical concept – inventory issues
- inventory of buildings, rooms and equipment (only so deep as necessary!!) - radiological classification of components, systems, buildings, areas - dose rate situation in rooms - waste inventory from operation
Planning tasks to be solved on this basis:
planning of - working hours per room / dose estimation - preliminary actions as decontamination for dose reduction before dismantling
planning of possible mass flow intensity and of containers for storing of dismantled material and waste
determination of material for further conditioning and treatment
determination of necessary buffer storages and treatment possibilities
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Technical concept – inventory (mass flow)
NPP Greifswald 1 800 000 Mg
Category 1 ~ 1 235 000 Mg
Plant parts TH 1 - 6, CA 6 ~ 50 000 Mg Building structure ~1 185 000 Mg
2/
Radioactive material Category 2 and 3 ~ 565 000 Mg
3
1/
Plant parts TH 1 – 5, IH 1 - 5 ~ 68 000 Mg
Building Structure and concrete ~ 497 000 Mg
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
3
Project strategy / planning (main issues)
project analysis
key decisions
licensing strategy/project planning
project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents
project strategy/planning
project implementation
project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items
project definition (WBS)
project execution
registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Project definition Technical project structure Definition of main projects – as basic for the WBS (example EWN) all in all 6 Projects:
decommissioning and dismantling of unit 1 – 6 KGR
decommissioning and dismantling of KKR-unit
refurbishments (plant adaptation and new facilities)
construction of the new interim storage
waste management
site reuse preparation
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Project definition Work breakdown structure EWN
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items
project definition (WBS)
project execution
registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
clarification of content and scope of technical planning documents (PCD 0,1&2)
execution planning (pre-checking documents)
licensing procedure
Project implementation - Project execution Detailed planning
issuing of dismantling licence
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution Detailed planning
„Pre-checking document „ (PCD, German abbreviation VPU), requirement of authority before starting of any decom. work PCD‘s are to be submitted to the authorized experts to check these documents regarding the licence and technical rules
PCD in connection with KGR decommissioning (VPU 0, VPU1, VPU2)
PCD in connection with storage of residual materials
PCD in connection with adaptation of systems, refurbishment, new equipment, wall opening
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution Detailed planning PCD 1 (content) – Execution of cutting points between Systems to be dismantled and operation systems
•
Description of tasks
•
List of systems to be decommissioned
•
Catalogue of the mechanical, electrical and instrumentation cutting points
•
Adaptation of P&I flow sheets to show parts to be dismantled
•
Preconditions (removal of media, cleaning, decontamination, removal of hot spots)
•
Step by step working plan
•
Dismantling instruction to realize the cutting points
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution Detailed planning PCD 2 (content) – Dismantling execution •
List of systems to be dismantled
•
List of remaining systems
•
Kind of material,
•
mass per system and room (inventory database)
•
Preconditions for dismantling (wall opening, changing of remaining systems, new airlocks)
•
Step by step working plans
•
Dismantling instructions
•
Plan for dose assessment (>25 mSv)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution Detailed planning Principle of decommissioning
§7 facility- category IV
VPU 1
Free release through authorized expert
VPU 2
Sign of cuttig points
Realisation of cutting points
Emptying cleaning
Confirmation of cutting points
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution Detailed planning
PCD 1 implementation example - Electrical cutting point IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution Detailed planning
PCD 1 implementation example - Cutting points of reactor IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items
project definition (WBS)
project execution
registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Registration of actual data
OD
claiming of working orders
PM
used manpower
registration of dismantled material (mass flow supervision)
invoice of contractors (services)
kg
direct costs
time consumption
schedule/ mile stones
checking period: bi-weekly / monthly checking level: working package (activities) IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items
project definition (WBS)
project execution
registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents
project strategy/planning
project implementation
project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling – Controlling level working packages
Estimated costs
Basic time schedule
Project controlling
top down
Project Part project Program
Time
bottom up
Detailed time schedule
Working package
Costs
Activity Action Task
Detailed project controlling
Nominal costs
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling – Basic time schedule
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling – Time schedule planning time schedule planning by Project Engineers •
based on
- mile stones and dependencies - different project structure levels - licensing conditions - basic time schedule and budget
supervision of realisation by Project Managers (Controlling) •
•
continuous inquiry of actual data and comparison with nominal data (planned or calculated) according to: - mass (kg) - manpower (mh) - costs (€) - time consumption (d) calculation of actual cost specific factors and correction factor
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling – Actual controlling actual controlling by PM (controlling department)
assessment of differences between actual and nominal data
adaptation of cost specific factors and correction factors
control of manpower capacity (mh) and dismantling productivity (kg/mh)
feedback of correlated factors into the planning tool of the DeManS (decommissioning management system)
shifting of working packages outside the critical path on time (smoothing of capacity peaks)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
c o n v e n tio n a l b u i ld in g d e m o l i ti o n
a u th o rit y c o n t ro l e x e m p ti o n a u t o m i c la w
s ta rt m e ss ure m en t b uil d in g
u n it 3 + 4 a n d w e t f ue l s to ra g e
u ni t 1 + 2
s ta r t d i s m a n t l i n g
Project management / controlling – Actual controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
c o n v e n t i o n a l b u i l d in g d e m o li ti o n
a ut h o ri ty c o n t ro l e x e m p t i o n a u t om i c law
s tart m e ss u re me n t b uil di n g
un it 3 + 4 a n d w e t f ue l s to ra ge
u ni t 1 + 2
s ta rt d i s m a n tl in g
Project management / controlling – Actual controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling – Reporting and documentation
reports on actual status of project performance
estimation of project performance (forecast)
preparation of management decisions in advance to the project revision (to change the project strategy)
preparation / justification and issue of a new revision of the project performance (each two years)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling – Actual controlling Optimisation of the whole decommissioning process Practical results - dismantling of big components and decay storage reactors (part 1), SG, pressurizers: • Shorten project time– ca. 3 a • Decrease of overall cost – ca. 15% – – – – –
(apr. 250 Mill.€) by: shorter remaining operation phase optimisation of container costs minimisation of final storage volume easier treatment condition due decay time lower personnel costs
Decommissioning Costs KGR
Mio. €
Concept planning
7.63
Licensing (ca. 4%)
65.83
Project controlling (ca. 1%)
14.54
Dismantling monitored area (ca. 3%)
43.45
Remote dismantling (ca. 7%)
113.11
Dismantling controlled area overall dismantling (ca. 4%)
67.47
Refurbishing (ca. 7%)
121.12
Material (Waste) Management (ca. 25%)
386.82
Remaining operation (ca. 50%)
833.00
1,653.0 0 IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents
project strategy/planning
project implementation
project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Thank you for your attention !
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012