Case Study Project Management and Project Planning

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012 Case Study Project Management and Project Planning...

9 downloads 1030 Views 2MB Size
Case Study Project Management and Project Planning Decommissioning Project Greifswald Axel Bäcker

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management & planning

Contents 

project strategy/planning



project implementation



project management/controlling

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues)



project analysis



key decisions



licensing strategy/project planning



project planning/technical concept

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis

Basic tasks and objectives  investigation of scenarios for the company strategy  timely sequence of main tasks  planning of the necessary personnel (qualification measures)  evalution of alternatives (technical, personnel)

ã definition of the company strategy (decommissioning main goals)

ã WBS creation (part projects definition)

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis

Steps system analysis à

definition of the overall strategy

detailed analysis for main issues à

technical strategy

à

personnel development

à

cost development

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis Main considerations • • • • • •

(fuel management) Material (waste) management & mass flow logistic dismantling strategy post operation personnel strategy site reuse options

 define main dependencies between activities  define mile stones and overall project life time  prepare key decision plan (with arguments) HOW to do it??

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis Practical realisation

Basis for the decision making process (system analysis)

DECISION TREE

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis Decision tree dismantling

Energiewerke Nord Energiewerke NordGmbH GmbH Unternehmensentwicklung Stillegung und Abbau

1990

ja

Unternehmensentwicklung integrierte Standortentwicklung

1990

nein

1

Personalstrategie AR-Beschluß 1990 sicherer Einschluß nein

Ende

ja

2

Unterstützung Region, aktive Öffentlichkeitsarbeit

1991

Flächenrecycling und Demontage Altanlagen

nein

3

1991

Stillegungskonzeptstudie EWN, KAH, NIS Ende

ja ABBAU BRENNELEMENTE

STILLEGUNGSABFÄLLE

BETRIEBSABFÄLLE

STANDORTBETRIEB

NACHBETRIEB

32

nein

Industriebrache

ja

1992

defekte Brennelemente

aus freien Marktgründen nur teilweise realisiert

feste Abfälle

ja

ja

nein

33

nein

Einlagerung Morsleben

1993

10

7

25

Konditionierung mobile Anlage

Konditionierung ZLN

ja

nein

ja nein

ja

ja

14

16

nein

aus Wirtschaftlichkeitsbetrachtungen aufgegeben

nein

Ende

nein

Ende Bereitstellung Sonderbehälter und Handhabungstechnik

1995

Konfektionierung vor Ort oder ZLN Ende

Schmelzanlage/ Verdampferanlage EWN nein

15

nein

5

ZLN

Schmelzanlage Extern/ Verdampferanlage ZLN Ende

Ende

ja

nein

28

Ende

nein Personalausstellung

ja

nein

29

nein

Restbetrieb

ja Abbau mit Fremdunternehmen

19

nein

ZLN

24

nur Halle 7

ja

ja

Ende

nein

ja

37

1994

39

Personalausstellung

ja

nein Personalausstellung Ende

Personaltransfer zu Stillegung und Abbau

ja (EWN)

38

1995

nein (§ 249 h)

ja

Realisierung Infrastruktur für Investorprojekte

Personalausstellung Ende

Ende

21

Block 5, KKR-MH geklärt

22

1996

abhängig von Realisierung TTC und Privatisierungs-/ Industrialisierungskonzepten

nein

Personalumsetzung möglich bis Bereitstellung Abbautechnik

Ende Entwicklung Technik Castor/Pollux

36

Ende

ja

Ende

nein

Personaltransfer zu Stillegung und Abbau

Ende

Abbautechniken verfügbar

Ende

Umlagerung Castor ZLN

ja

35

Personalausstellung

Terminverzug 1:1

nein

20

Beräumung unterirdische Wirtschaft

Ende

30

Ende

1993 nein

Ende

Personalzuordnung zum Stellenplan Stillegung und Abbau

ja

stationäre Anlage Zustandsanalyse konform Erwartungen

34

Personaltransfer zu Stillegung und Abbau

Ende

nein

Ende

Anpassung Infrastruktur für Investorprojekte

ja

23

ja

Rekultivierung

Erschließung der Flächen für Neuanlagen

Qualifikation vorhanden ja

ja

nein Ende

KRB-MOX

1997

nein

26

Nachqualifizierung

Personaltransfer zu Stillegung und Abbau

Stillegungsgenehmigung

1996 Castor ZLN

Umlagerung des Personals bei Ausgliederung

ja

ja

ja ja

ja

nein

nein

27

Ausgliederung nach § 613 a BGB

nein

18

keine Rückstellung für KGR, KKR Gebäudeabriß

8 Ende

Modellprojekt Block 5-8 Teilstillegungsvorhaben

nein

Konfektionierung ZAW

ja 11

ja

ja 13

Bereitstellung VERA + weitere Lagerkapazität

Castor Block 1-5 bzw. Rheinsberg

nein

Einsatz und Auswahl EWN-Stammpersonal für Stillegung und Abbau ja

nein

Ende

1994

yes 17

Einlagerung ZAB nein

Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von Betriebseinheiten

complete dismantling no

ja

6 nein

1992

nein 12

4 Transporttechnik für Einlagerung verfügbar

Ende

Entwicklung zum Energie- und Industriestandort

nein

1997

Personalausstellung Ende

Personaleinsatz außerhalb EWN ja

1998

31

BE-Wiederaufarbeitung ja

9

nein

nein

Aufbau Stillegungs- und Standortbetreibergesellschaft

schrittweise Personalausstellung

Ende

Endlager

Endlager

Erhaltung Reststruktur

Privatisierung

Ende

Ende

Ende

Ende

1998 Referenzstrategie Strategiealternativen

Ende

Direkte Endlagerung Ende

programm-, personal- und terminbestimmende Meilensteine

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis Decision tree waste management

Energiewerke Nord Energiewerke NordGmbH GmbH Unternehmensentwicklung Stillegung und Abbau

1990

ja

Unternehmensentwicklung integrierte Standortentwicklung

1990

nein

1

Personalstrategie AR-Beschluß 1990 sicherer Einschluß nein

Ende

ja

2

Unterstützung Region, aktive Öffentlichkeitsarbeit

1991

Flächenrecycling und Demontage Altanlagen

nein

3

1991

Stillegungskonzeptstudie EWN, KAH, NIS Ende

ja ABBAU BRENNELEMENTE

STILLEGUNGSABFÄLLE

BETRIEBSABFÄLLE

STANDORTBETRIEB

NACHBETRIEB

32

nein

Industriebrache

ja

1992

defekte Brennelemente

aus freien Marktgründen nur teilweise realisiert

feste Abfälle

ja

ja

nein

33

nein

Disposal Morsleben

1993

10

ja

ja

14

16

nein nein

aus Wirtschaftlichkeitsbetrachtungen aufgegeben

nein

Ende

nein

Ende Bereitstellung Sonderbehälter und Handhabungstechnik

1995

Konfektionierung vor Ort oder ZLN Ende

Schmelzanlage/ Verdampferanlage EWN nein

15

nein

5

ZLN

Schmelzanlage Extern/ Verdampferanlage ZLN Ende

Ende

ja

nein

28

Ende

nein Personalausstellung

ja

nein

29

nein

Restbetrieb

ja Abbau mit Fremdunternehmen

19

nein

ZLN

24

nur Halle 7

ja

ja

Ende

nein

ja

37

1994

39

Personalausstellung

ja

nein Personalausstellung Ende

Personaltransfer zu Stillegung und Abbau

ja (EWN)

38

1995

nein (§ 249 h)

ja

Realisierung Infrastruktur für Investorprojekte

Personalausstellung Ende

Ende

21

Block 5, KKR-MH geklärt

22

1996

abhängig von Realisierung TTC und Privatisierungs-/ Industrialisierungskonzepten

nein

Personalumsetzung möglich bis Bereitstellung Abbautechnik

Ende Entwicklung Technik Castor/Pollux

36

Ende

ja

Ende

nein

Personaltransfer zu Stillegung und Abbau

Ende

Abbautechniken verfügbar

Ende

Umlagerung Castor ZLN

ja

35

Personalausstellung

Terminverzug 1:1

nein

20

Beräumung unterirdische Wirtschaft

Ende

30

Ende

1993 nein

Ende

Personalzuordnung zum Stellenplan Stillegung und Abbau

ja

stationäre Anlage Zustandsanalyse konform Erwartungen

34

Personaltransfer zu Stillegung und Abbau

Ende

nein

Ende

Anpassung Infrastruktur für Investorprojekte

ja

23

ja

Rekultivierung

Erschließung der Flächen für Neuanlagen

Qualifikation vorhanden ja

ja

nein Ende

KRB-MOX

1997

nein

26

Nachqualifizierung

Personaltransfer zu Stillegung und Abbau

Stillegungsgenehmigung

1996 Castor ZLN

Umlagerung des Personals bei Ausgliederung

ja

ja

ja ja

ja

nein

nein

27

Ausgliederung nach § 613 a BGB

nein

18

keine Rückstellung für KGR, KKR Gebäudeabriß

8 Ende

Modellprojekt Block 5-8 Teilstillegungsvorhaben

nein

Konfektionierung ZAW

ja 11

ja

ja 13

Additional storages

Castor Block 1-5 bzw. Rheinsberg

nein

25

Konditionierung mobile Anlage

Konditionierung ZLN nein

Einsatz und Auswahl EWN-Stammpersonal für Stillegung und Abbau ja

ja stop

1994

17

no

yes 7

aus Rückstellungsgründen nur teilweise realisiert

ja

nein

Einlagerung ZAB nein

Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von Betriebseinheiten

kompletter Rückbau

ja

6 nein

1992

nein 12

4 Transporttechnik für Einlagerung verfügbar

Ende

Entwicklung zum Energie- und Industriestandort

nein

1997

Personalausstellung Ende

Personaleinsatz außerhalb EWN ja

1998

31

BE-Wiederaufarbeitung ja

9

nein

nein

Aufbau Stillegungs- und Standortbetreibergesellschaft

schrittweise Personalausstellung

Ende

Endlager

Endlager

Erhaltung Reststruktur

Privatisierung

Ende

Ende

Ende

Ende

1998 Referenzstrategie Strategiealternativen

Ende

Direkte Endlagerung Ende

programm-, personal- und terminbestimmende Meilensteine

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Project analysis Overall decision tree EWN

Energiewerke Nord GmbH Unternehmensentwicklung Stillegung und Abbau

1990

ja

Site reuse

1990

nein

1

Personnel strategy AR-Beschluß 1990 sicherer Einschluß nein

Ende

ja

2

Unterstützung Region, aktive Öffentlichkeitsarbeit

1991

Flächenrecycling und Demontage Altanlagen

nein

3

Ende

ja

Fuel elements

Dismantling material

Operational waste

1991

Stillegungskonzeptstudie EWN, KAH, NIS

Dismantling

STANDORTBETRIEB

Post operation

32

nein

Industriebrache

ja

1992

defekte Brennelemente

aus freien Marktgründen nur teilweise realisiert

feste Abfälle

ja

ja

nein

33

nein

Einlagerung Morsleben nein

nein

10

Einlagerung ZAB 7

nein

ja

ja

14

16

aus Wirtschaftlichkeitsbetrachtungen aufgegeben

Ende

Ende

nein

keine Rückstellung für KGR, KKR Gebäudeabriß

nein

Ende Bereitstellung Sonderbehälter und Handhabungstechnik

Modellprojekt Block 5-8 Teilstillegungsvorhaben

Konfektionierung vor Ort oder ZLN Ende

Schmelzanlage/ Verdampferanlage EWN nein

15

nein

ZLN

5

Schmelzanlage Extern/ Verdampferanlage ZLN Ende

Ende

ZLN

nur Halle 7

ja

nein

28

nein

29

nein

ja

nein Personalausstellung

Restbetrieb

ja Abbau mit Fremdunternehmen

nein

24

ja

ja

Umlagerung Castor ZLN

Ende

21

ja

nein Personalausstellung Ende

Personaltransfer zu Stillegung und Abbau

ja (EWN)

38

1995

nein (§ 249 h)

ja

Realisierung Infrastruktur für Investorprojekte

Personalausstellung Ende

Ende

Block 5, KKR-MH geklärt

22

1996

abhängig von Realisierung TTC und Privatisierungs-/ Industrialisierungskonzepten

nein

Personalumsetzung möglich bis Bereitstellung Abbautechnik

Ende Entwicklung Technik Castor/Pollux

39

Personalausstellung

Ende

ja

Ende

1994

Ende

Abbautechniken verfügbar

Ende

nein

Personalausstellung

Terminverzug 1:1

nein

20

36

ja

37

Personaltransfer zu Stillegung und Abbau

Ende

30 Zustandsanalyse konform Erwartungen

Beräumung unterirdische Wirtschaft

nein

Ende

Personalzuordnung zum Stellenplan Stillegung und Abbau

ja

1993 nein

ja

35

Personaltransfer zu Stillegung und Abbau

Ende

nein

19

34

Anpassung Infrastruktur für Investorprojekte

Nachqualifizierung ja

stationäre Anlage Ende

Ende

Erschließung der Flächen für Neuanlagen

Qualifikation vorhanden ja

ja

nein Ende

KRB-MOX

1997

nein

26

Ende

23

ja

Stillegungsgenehmigung

1996 Castor ZLN

ja

Rekultivierung

nein

27

ja

ja ja

ja

Umlagerung des Personals bei Ausgliederung

Ausgliederung nach § 613 a BGB Personaltransfer zu Stillegung und Abbau

nein

18

8

1995

25 nein

nein

nein

Konfektionierung ZAW

ja

11

ja

nein

ja 13

Bereitstellung VERA + weitere Lagerkapazität

Castor Block 1-5 bzw. Rheinsberg

1994

Konditionierung mobile Anlage

Konditionierung ZLN

ja

aus Rückstellungsgründen nur teilweise realisiert

ja Ende

Einsatz und Auswahl EWN-Stammpersonal für Stillegung und Abbau

nein

ja

17

nein

ja nein

Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von Betriebseinheiten

kompletter Rückbau

ja

6

1993

1992

nein 12

4 Transporttechnik für Einlagerung verfügbar

Ende

Entwicklung zum Energie- und Industriestandort

nein

1997

Personalausstellung Ende

Personaleinsatz außerhalb EWN ja

1998

31

BE-Wiederaufarbeitung ja

9

nein

nein

Aufbau Stillegungs- und Standortbetreibergesellschaft

schrittweise Personalausstellung

Ende

Endlager

Endlager

Erhaltung Reststruktur

Privatisierung

Ende

Ende

Ende

Ende

1998 Referenzstrategie Strategiealternativen

Ende

Direkte Endlagerung Ende

programm-, personal- und terminbestimmende Meilensteine

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues)



project analysis



key decisions



licensing strategy/project planning



project planning/technical concept

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning – EWN initial key decisions

 Direct dismantling no Safe Enclosure

 Introduce project organization  Project realisation by own staff instead of contractors  Erect major interim store on-site for fuel, waste and treatment  Reuse of site for industrial and energetic uses

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues)



project analysis



key decisions



licensing strategy/project planning



project planning/technical concept

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Licensing strategy/project planning -step by step procedure basic documents for dismantling project p a r t o f

o v e r a l l

license 1995

application for dismantling license

issue of dismantling license

pre checking documents

Explanatory reports on - fire protection - dismantling - radiation protection - remote dismantling - waste management Operation manual - procedures of operation systems - radiaton protection ordinance - decommissioning and dismantling ordinance Technical planning: - which parts should be dismantled - which parts should be remained Authority of the country Mecklenburg-Vorpommern

Authorised expert (technical control organisation, experts of fire protection, site safety )

VPU 0 VPU 1

VPU 2

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues)



project analysis



key decisions



licensing strategy/project planning



project planning/technical concept

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Technical concept - contents



main decommissioning and dismantling steps

   

dismantling principles operational waste management categorisation of systems/buildings/areas by radiological classes inventorisation

   

mass flow logistic (from dismantling) main items of necessary plant adaptations main items of investments (new equipment, new installations) special dismantling and disposal concept for highly activated components safe post operation, evaluation of the residual life time of old equipment possibilities to reduce costs (alternatives)

 

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Technical concept – dismantling principles



dismantling planning on system basic, execution on room basis



start in unit 5; low contamination / radiation dose



from low to high contamination / radiation dose



use market equipment



in situ decontamination only for dose reduction



whole components / parts as possible for decay or treatment in interim storage

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Technical concept – material categorisation Radiological classes

category I

unrestricted material from the monitored area which is not subject to the release measurement procedure

category II

suspected material (an eventual contamination cannot be excluded) from the monitored area, mainly from the turbine hall

category III

contaminated material

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Technical concept – inventory issues 

- inventory of buildings, rooms and equipment (only so deep as necessary!!) - radiological classification of components, systems, buildings, areas - dose rate situation in rooms - waste inventory from operation

Planning tasks to be solved on this basis: 

planning of - working hours per room / dose estimation - preliminary actions as decontamination for dose reduction before dismantling



planning of possible mass flow intensity and of containers for storing of dismantled material and waste



determination of material for further conditioning and treatment



determination of necessary buffer storages and treatment possibilities

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project strategy / planning (main issues) – Technical concept – inventory (mass flow)

NPP Greifswald 1 800 000 Mg

Category 1 ~ 1 235 000 Mg

Plant parts TH 1 - 6, CA 6 ~ 50 000 Mg Building structure ~1 185 000 Mg

2/

Radioactive material Category 2 and 3 ~ 565 000 Mg

3

1/

Plant parts TH 1 – 5, IH 1 - 5 ~ 68 000 Mg

Building Structure and concrete ~ 497 000 Mg

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

3

Project strategy / planning (main issues)



project analysis



key decisions



licensing strategy/project planning



project planning/technical concept

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management & planning

Contents 

project strategy/planning



project implementation



project management/controlling

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Main items



project definition (WBS)



project execution



registration of actual data

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Project definition Technical project structure Definition of main projects – as basic for the WBS (example EWN) all in all 6 Projects:



decommissioning and dismantling of unit 1 – 6 KGR



decommissioning and dismantling of KKR-unit



refurbishments (plant adaptation and new facilities)



construction of the new interim storage



waste management



site reuse preparation

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Project definition Work breakdown structure EWN

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Main items



project definition (WBS)



project execution



registration of actual data

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

clarification of content and scope of technical planning documents (PCD 0,1&2)

execution planning (pre-checking documents)

licensing procedure

Project implementation - Project execution Detailed planning

issuing of dismantling licence

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation - Project execution Detailed planning

„Pre-checking document „ (PCD, German abbreviation VPU), requirement of authority before starting of any decom. work PCD‘s are to be submitted to the authorized experts to check these documents regarding the licence and technical rules

PCD in connection with KGR decommissioning (VPU 0, VPU1, VPU2)

PCD in connection with storage of residual materials

PCD in connection with adaptation of systems, refurbishment, new equipment, wall opening

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation - Project execution Detailed planning PCD 1 (content) – Execution of cutting points between Systems to be dismantled and operation systems



Description of tasks



List of systems to be decommissioned



Catalogue of the mechanical, electrical and instrumentation cutting points



Adaptation of P&I flow sheets to show parts to be dismantled



Preconditions (removal of media, cleaning, decontamination, removal of hot spots)



Step by step working plan



Dismantling instruction to realize the cutting points

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation - Project execution Detailed planning PCD 2 (content) – Dismantling execution •

List of systems to be dismantled



List of remaining systems



Kind of material,



mass per system and room (inventory database)



Preconditions for dismantling (wall opening, changing of remaining systems, new airlocks)



Step by step working plans



Dismantling instructions



Plan for dose assessment (>25 mSv)

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation - Project execution Detailed planning Principle of decommissioning

§7 facility- category IV

VPU 1

Free release through authorized expert

VPU 2

Sign of cuttig points

Realisation of cutting points

Emptying cleaning

Confirmation of cutting points

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation - Project execution Detailed planning

PCD 1 implementation example - Electrical cutting point IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation - Project execution Detailed planning

PCD 1 implementation example - Cutting points of reactor IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Main items



project definition (WBS)



project execution



registration of actual data

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Registration of actual data

OD

claiming of working orders

PM

used manpower

registration of dismantled material (mass flow supervision)

invoice of contractors (services)

kg

direct costs

time consumption

schedule/ mile stones

checking period: bi-weekly / monthly checking level: working package (activities) IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project implementation – Main items



project definition (WBS)



project execution



registration of actual data

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management & planning

Contents 

project strategy/planning



project implementation



project management/controlling

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management / controlling – Controlling level working packages

Estimated costs

Basic time schedule

Project controlling

top down

Project Part project Program

Time

bottom up

Detailed time schedule

Working package

Costs

Activity Action Task

Detailed project controlling

Nominal costs

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management / controlling – Basic time schedule

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management / controlling – Time schedule planning time schedule planning by Project Engineers •

based on

- mile stones and dependencies - different project structure levels - licensing conditions - basic time schedule and budget

supervision of realisation by Project Managers (Controlling) •



continuous inquiry of actual data and comparison with nominal data (planned or calculated) according to: - mass (kg) - manpower (mh) - costs (€) - time consumption (d) calculation of actual cost specific factors and correction factor

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management / controlling – Actual controlling actual controlling by PM (controlling department) 

assessment of differences between actual and nominal data



adaptation of cost specific factors and correction factors



control of manpower capacity (mh) and dismantling productivity (kg/mh)



feedback of correlated factors into the planning tool of the DeManS (decommissioning management system)



shifting of working packages outside the critical path on time (smoothing of capacity peaks)

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

c o n v e n tio n a l b u i ld in g d e m o l i ti o n

a u th o rit y c o n t ro l e x e m p ti o n a u t o m i c la w

s ta rt m e ss ure m en t b uil d in g

u n it 3 + 4 a n d w e t f ue l s to ra g e

u ni t 1 + 2

s ta r t d i s m a n t l i n g

Project management / controlling – Actual controlling

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

c o n v e n t i o n a l b u i l d in g d e m o li ti o n

a ut h o ri ty c o n t ro l e x e m p t i o n a u t om i c law

s tart m e ss u re me n t b uil di n g

un it 3 + 4 a n d w e t f ue l s to ra ge

u ni t 1 + 2

s ta rt d i s m a n tl in g

Project management / controlling – Actual controlling

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management / controlling – Reporting and documentation



reports on actual status of project performance



estimation of project performance (forecast)



preparation of management decisions in advance to the project revision (to change the project strategy)



preparation / justification and issue of a new revision of the project performance (each two years)

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management / controlling – Actual controlling Optimisation of the whole decommissioning process Practical results - dismantling of big components and decay storage reactors (part 1), SG, pressurizers: • Shorten project time– ca. 3 a • Decrease of overall cost – ca. 15% – – – – –

(apr. 250 Mill.€) by: shorter remaining operation phase optimisation of container costs minimisation of final storage volume easier treatment condition due decay time lower personnel costs

Decommissioning Costs KGR

Mio. €

Concept planning

7.63

Licensing (ca. 4%)

65.83

Project controlling (ca. 1%)

14.54

Dismantling monitored area (ca. 3%)

43.45

Remote dismantling (ca. 7%)

113.11

Dismantling controlled area overall dismantling (ca. 4%)

67.47

Refurbishing (ca. 7%)

121.12

Material (Waste) Management (ca. 25%)

386.82

Remaining operation (ca. 50%)

833.00

1,653.0 0 IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Project management & planning

Contents 

project strategy/planning



project implementation



project management/controlling

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012

Thank you for your attention !

IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012