Pacific Gas & Electric Company Note: To be qualified on a PG&E task, you must complete the following steps (order is not important): 1) Complete the on-line training and exam(s) for all corresponding Veriforce CCTs and/or PG&E tasks (frequency is based on CCT or PG&E requirements) 2) Be successfully evaluated for all corresponding Veriforce CCTs and/or PG&E tasks (frequency is based on CCT or PG&E requirements) 3) Review and acknowledge understanding of applicable PG&E procedures (annual requirement) 4) Successfully complete the applicable PG&E on-line exam (annual requirement) 5) Review and acknowledge the PG&E AOC Job Aid (annual requirement) 6) Review and acknowledge the PG&E Onboarding Training

PG&E CT # Task Description

SOC

Requal Int

Trng Method

Eval Method

CCT(s), Corresponding CCT CBT(s), PG&E task(s), and Corresponding PG&E Task CBT(s)

Additional PG&E Requirements

Applicable PG&E Procedure(s)

01-02.00

Protect Cast Iron Pipeline

1:1

1 yr

CBT/Exam

Oral

PGE01-02

01-03.00

Operations and Maintenance

1:1

1 yr

CBT/Exam

Obs/Oral

780

Gas Standard - A-39, AOC Appendix

02-01.00

Mechanical Repairs

1:1

1 yr

CBT/Exam

Obs/Oral

216

613

02-02.00

Weld Repairs

1:0

1 yr

CBT/Exam

Obs/Oral

616

708

02-03.00

Pipe Squeezing Steel

1:1

1 yr

CBT/Exam

Obs/Oral

764

02-04.00

Pipe Squeezing - Plastic

1:1

1 yr

CBT/Exam

Obs/Oral

763

02-06.00

Abandonment or Deactivation Pipeline Facilities

1:1

1 yr

CBT/Exam

Obs/Oral

007

614

02-07.00

Pipeline Replacement

1:1

1 yr

CBT/Exam

Obs/Oral

502

613

02-11.00

Install and Backfill Pipe in Ditch – Plastic

1:1

3yr

CBT/OJT

Written Exam

OJT PGE 02-11

A-04, A-90, A- 90.2, A-91, A-93.1, A-93, EMS-4123, L-16, PG&E Greenbook, S5453 Attachment 1, S5453, Exhibit B, TD-4008S Attachment 1

02-12.00

Install Pipe in a Bore

1:1

3yr

CBT/OJT

Written Exam

OJT PGE 02-12

A-90, A-90.2, A-93.1, M-16.2, O-12, S5453 Attachment 1, S5453 Exhibit B, TD-4412P-05, TD-4412B-017

02-13.00

Install and Backfill in Ditch (plastic/steel)

1:1

3yr

CBT/OJT

Written Exam

OJT PGE 02-13

A-04, A-34, A-36, A-90, A-90.2, A-91, A-93, A-93.1, E-25, L-16, EMS-4123, PG&E Greenbook, S5453, S5453 Attachment 1, S5453 Exhibit B, TD-4412P-05 Attachment 1, TD-4008S Attachment 1

02-14.00

Tracer Wire

1:1

3yr

CBT

Obs/Oral

PGE 02-14

03-03.00

Rectifier Reads

1:1

1 yr

CBT/Exam

Obs/Oral

408

Universal Variac Rectifier Troubleshooting Job Aid, TD-4008P-01, TD-4180P-204, TD-4181P-201, TD-4181P-301, TD-4181B-004, AOC Appendix

03-04.00

Atmospheric Corrosion / Monitor

1:1

1 yr

CBT/Exam

Oral

417

E-30, TD-4188P-01, TD-4188P-02, AOC Appendix

03-05.00

Pipe Inspection

1:1

1 yr

CBT/Exam

Oral

401

TD-4008P-01, Attachment 4_AOC Document, TD-4100P-05, TD-4186S, TD-4711P-01, A-34, E-25, E-30, TD-5100P-01, A-93, AOC Appendix

03-06.00

Pipe-to-Soil Reads

1:1

1 yr

CBT/Exam

Obs/Oral

419

TD-4008P-01, Attachment 4_AOC Document, TD-4180P-202, TD-4180P-204, TD-4181P-202, TD-4181P-201, AOC Appendix

03-07.00

Cathodic Protection Maintenance

1:1

1 yr

CBT/Exam

Obs/Oral

407

03-08.00

Galvanic Anode Maintenance

1:1

1 yr

CBT/Exam

Obs/Oral

419

Corrosion Manual O-13.1, TD-4181P-201,TD-4008P-01, Attachment 4_AOC Document, TD-4181B-004, AOC Appendix

03-10.00

Rectifier Maintenance

1:1

1 yr

CBT/Exam

Obs/Oral

408

AC Induction Job Aid, AC Switchbox Troubleshooting Job Aid, CT235 AC/DC Probe Job Aid, Goodall Rectifier Troubleshooting Job Aid, Ground Resistance Tester Job Aid, Universal Tap Rectifier Troubleshooting Job Aid, Universal Variac Rectifier Troubleshooting Job Aid,TD-4414P-03, TD-4181P-201, AOC Appendix

03-11.00

O-22, O-22.1, M-84, TD-4181P-201, TD-4181P-601, TD-4008P-01, Attachment 4_AOC Document, AOC Appendix

Gas Standards - A-44, B-50.1, B-53, B-54.1, B-54.2, C-37, AOC Appendix 707 708

Gas Standards - B-53, B-53.1, B-53.2, B-54, AOC Appendix Gas Standards - A-60, A-61, A-63, A-64, D-30, D-30.2, D-30.4, TD-4100P-05, TD-4160P-20, TD-4160P-30, TD-4160P-31, AOC Appendix Gas Standards - M-22.2, M-24.1, AOC Appendix A-93.1, TD-4170P-02 JA1, TD-4170P-02 JA2, WP 4170-02, AOC Appendix Gas Standards - A-38, A-93.2, TD-9500P-16, Attachments 1-3, AOC Appendix

614

Gas Standards - A-34, A-38, A-93.1, M-16.2, AOC Appendix

A-90.2, O-12, PG&E Greenbook, TD-4008S Attachment 1

Corrosion Manual O-16, WP-4133-03, AC Induction Job Aid, AC Switchbox Troubleshooting Job Aid, CT235 AC/DC Current Probe Job Aid, Current Spanning-How to Conduct Job Aid, Deep Well Anode-Troubleshooting for No Current Job Aid, Deep Well Anode-Flushing Job Aid, Goodall Rectifier Troubleshooting Job Aid, Ground Resistance Tester Job Aid, Interference Testing-How to Conduct Job Aid, Multimeter Guide-How to Perform Conductivity Test Job Aid, Multimeter-How to Set-Up for Spanning Job Aid, Universal Tap Rectifier Troubleshooting Job Aid, Universal Variac Rectifier Troubleshooting Job Aid, TD-4181P-201 , TD-4181P-601, TD-4181P-301, TD-4008P-01, Attachment 4_AOC Document , AOC Appendix

420

Testing/Inspecting for Adequate Electrical Isolation

1:1

1 yr

CBT/Exam

Obs/Oral

411

03-14

Attaching Electrical Connections to Steel Pipe using Exothermic Methods

1:1

3 yrs

CBT/Exam

Obs/Oral

PGE 03-14

03-15

Attaching Electrical Connections to Steel Pipe Using Pin Brazing Method

1:1

3 yrs

CBT/Exam

Written/Oral

PGE 03-15

03-17

Coating App and Repair: Wrapped

1:1

1 yr

CBT/Exam

Obs/Oral

PGE 03-17

484

E-25, E-35

03-18

Coating App and Repair: Hand Epoxy

1:1

1 yr

CBT/Exam

Obs/Oral

PGE 03-18

480

Bulletin 191, CGT Standard 4132, E-30, E35, TD-E-35B-003

03-19

Coating App and Repair: Spray Epoxy

1:1

1 yr

CBT/Exam

Obs/Oral

PGE 03-19

482

Bulletin 191, CGT Standard 4132, E-30, E35, TD-E-35B-003

03-20

Paint App and Maint: Above Ground

1:1

1 yr

CBT/Exam

Obs/Oral

PGE 03-20

E-31

03-22

Abrasive Blasting

1:1

1 yr

CBT/Exam

Obs/Oral

PGE 03-22

E-35.5, WP4100-12, TD-E-35B-003, E-30, E-35

04-02.00

Strength Test

1:1

1 yr

CBT/Exam

Obs/Oral

501

Gas Standards A-34v04, TD-4137P-01, 4137P-02, 4137P-03, 4137P-04 (with attachments 1,2,3,5), STPR Form, AOC Appendix

04-03.00

Leak Test at Operating Pressure

1:1

1 yr

CBT/Exam

Obs/Oral

502

TD-4110P-03, M-13.4, AOC Appendix

04-04.00

Pressure Test for Facilities Operating below 100 psi (Leak Test)

1:1

1 yr

CBT/Exam

Obs/Oral

502

Gas Standards- A-34-(v04), A-93.1, M-13.4, TD-4008P-01, Attachment 4_AOC Document, AOC Appendix

05-01.00

Mark and Locate Facilities

1:1

1 yr

CBT/Exam

Obs/Oral

605

M-84, TD-4412B-004, TD-4412B-008, TD-4412P-01, TD-4412P-02, TT-4412P-02-F01, TD-4412P-03, TD-4412-03 Attachments 1-3, UO Standard S4412, WP-4412-04, User Manual Metrotech 850, User Manual Metrotech 9890XT, User Manual Vivax cLocPro, TD-5811P-103, TD-5811P-104, TD-5811P-105, TD-5811P-105-JA-02, TD-5811P-JA04, TD-5811P-201, TD-5811 Gas Map Symbols, TD-4008P-01 Attachment 4_AOC Document ,TD-511P103-JA01, TD-5811P-205, TD-5811P-301-JA01, TD-5811P-604

05-02.00 A

Standby Pipeline Task PGE 05-02 A & B can be used in place of PGE 05-07. PGE 05-07 is not acceptable in place of PGE 05-02 A & B

1:1

1 yr

CBT/Exam

Oral

607

619

05-02.00 B

Standby Pipeline Task PGE 05-02 A & B can be used in place of PGE 05-07. PGE 05-07 is not acceptable in place of PGE 05-02 A & B

1:1

1 yr

CBT/Exam

Oral

607

619

Location of Facilities Without Wire

1:1

1 yr

CBT/Exam

Obs/Oral

605

05-03.00

CADWELD_EWM_US_A, TD-4181P-502 TD-4181P-503, TD-4181S, O-10

Pipehorn Training

605

Gas Map Symbol Sheet_102013, TD-5811P-105-JA04, TD-5811P-301, TD-5811P-301-JA01, AOC Appendix

This will require task PGE 05-01.00 as a co- Gas Map Symbol Sheet_102013, TD-5811P-105-JA04, TD-5811P-301, TD-5811P-301-JA01, AOC Appendix requisite M-60.4, M-84, TD-4008P-01 Attachment 4_AOC Document, TD-4412P-11, TD-4412P-11-JA01, TD-5811P-105-JA02, TD5811P-105-JA03, UO Standard S4412, TD-5811P-605, TD-5811P-201, AOC Appendix

Page 1 of 3

Revision 32, January 04, 2018

Pacific Gas & Electric Company Note: To be qualified on a PG&E task, you must complete the following steps (order is not important): 1) Complete the on-line training and exam(s) for all corresponding Veriforce CCTs and/or PG&E tasks (frequency is based on CCT or PG&E requirements) 2) Be successfully evaluated for all corresponding Veriforce CCTs and/or PG&E tasks (frequency is based on CCT or PG&E requirements) 3) Review and acknowledge understanding of applicable PG&E procedures (annual requirement) 4) Successfully complete the applicable PG&E on-line exam (annual requirement) 5) Review and acknowledge the PG&E AOC Job Aid (annual requirement) 6) Review and acknowledge the PG&E Onboarding Training

PG&E CT # Task Description

SOC

Requal Int

Trng Method

Eval Method

CCT(s), Corresponding CCT CBT(s), PG&E task(s), and Corresponding PG&E Task CBT(s)

Additional PG&E Requirements

Applicable PG&E Procedure(s)

05-07.00

Damage Prevention During Excavation. Task PGE 05-02 A & B can be used in place of PGE 05-07. PGE 05-07 is not acceptable in place of PGE 05-02 A & B

1:0

3yr

CBT/OJT

Written Exam

06-01.00

Tap and plug a 3/4" - 2" service tee or a 1" - 2" Save-A-Valve using a Mueller drilling machine

1:1

1 yr

CBT/Exam

Obs/Oral

PGE06-01

611

Gas Standards - C-10, C-14, C-20.2, C-23, C-25, C-26, C-27, C-28, C-40, C-41, TD-4150P-100, TD-4150P-101, TD-4150P-102, TD-4150P-103, TD-4150P-120, TD-4150P-121, TD-4150P-122, TD-4150P-123, TD-4151M-JA02, TD-4151M-JA101, TD-4151M-JA121, TD-4151M-JA500, AOC Appendix

06-02.00

Tap and plug a 3/4" - 4" Mueller low pressure line stopper (M2) using a Mueller drilling machine

1:1

1 yr

CBT/Exam

Obs/Oral

611

762

C-15.3, C-16.4, C-20.2, C-25, C-26, C-27, C-28, C-29, C-40, C-41, S0454, TD-4150P-200, TD-4150P-201, TD-4150P-202, TD-4150P-203, TD-4151M-JA02, TD-4151M-JA201, TD-4151M-JA500, TD-4816S, AOC Appendix

06-03.00

Tap and plug a 3/4" - 2" split control fitting using a Mueller drilling machine

1:1

1 yr

CBT/Exam

Obs/Oral

611

762

C-15.3, C-20.2, C-23, C-25, C-26, C-27, C-28, C-29, C-40, C-41, S0454, TD-4150P-210, TD-4150P-211, TD-4150P-212, TD-4150P-213, TD-4151M-JA211, TD-4151M-JA500, TD-4186S, AOC Appendix

06-06.00

Hot/tap/branch connection

1:1

1 yr

CBT/Exam

Obs/Oral

611

762

Gas Standards - A-52, C-16, C-16.1, C-16.5, C-20, C-25, C-64.1, AOC Appendix

06-08.00

Low/semi high pressure bagging

1:1

1 yr

CBT/Exam

Obs/Oral

761

06-09.00

Low pressure drill and thread

1:1

1 yr

CBT/Exam

Oral

PGE06-09

06-12.00

Tap and plug a 3/4" - 2" Mueller Stop Tee (Valve tee, Pin-off tee) using a Mueller drilling machine

1:1

1 yr

CBT/Exam

Obs/Oral

611

06-13.00

PE tapping tee (outlet sizes ½" to 2")

1:1

1 yr

CBT/Exam

Oral

PGE06-13

06-14.00

PE hot tap/branch (McElroy), (2", 4")

1:1

1 yr

CBT/Exam

Obs/Oral

612

Gas Standards – A-93.1, A-93, B-90.3, D-34, WP 4170-09, AOC Appendix

06-15.00

PE hot tap/branch (1/2", 1" & 2")

1:1

1 yr

CBT/Exam

Obs/Oral

612

Gas Standards – A-93.1, B-90.1, D-34, WP 4170-09, AOC Appendix

1:1

1 yr

CBT/Exam

Obs/Oral

PGE06-01

Gas Standards C-10, TD-4150P-104, TD-4150P-JA01, TD-4150P-JA02, TD-4151M-JA101, TD-4151M-JA500, AOC Appendix

1:1

1 yr

CBT/Exam

Obs/Oral

PGE06-17

TD-4150P-109, TD-4151M-JA101, TD-4151M-JA500, TD-4150P-110, AOC Appendix

1:1

1 yr

CBT/Exam

Obs/Oral

PGE06-18

06-16.00 06-17.00 06-18.00

Plug a 3/4" - 1-1/4" service tee using the Mueller H-17045 completion machine & the Mueller H-17040 stopping machine Tap a service tee using the built-in cutter (coupon retaining punch) Stop a ¾" - 2" service tee at low pressure (less than 0.25 PSIG) using the Grunsky bag and X-pando plugs

OJT PGE 05-07

TD-4008S Attachment 1, TD-4110P-09, TD-4412P-05 vs 2, TD-5811P-301, TD-5811P-1200, TD-9510P-01

C-37, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix C-37, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix Gas Standards - C-11, TD-4150P-130, TD-4150P-131, TD-4151M-JA02, TD-4151M-JA131, TD-4151M-JA500, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix Gas Standards – A-93.1, B-90.1, B-90.2, D-34, WP 4170-09, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix

TD-4150P-105, TD-4151M-JA101, TD-4151M-JA500, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix

06-22.00

Tap a 2" - 4" side tap extension stopper under 60 PSIG using a Mueller D-series drilling machine

1:1

1 yr

CBT/Exam

Obs/Oral

611

07-01.00

Air Purging

1:1

1 yr

CBT/Exam

Oral

614

Gas Standard - A-38, AOC Appendix

07-02.00

Gas Purging

1:1

1 yr

CBT/Exam

Oral

613

Gas Standards - A-38, AOC Appendix

07-03.00

Inert Purging

1:1

1 yr

CBT/Exam

Oral

614

07-04.00

Air Mover Operations

1:1

1 yr

CBT/Exam

Obs/Oral

614

08-01.00

Inspect and Maintain Transmission Line

1:1

1 yr

CBT/Exam

Oral

701

762

Gas Standards - C-16.5, C-41, D-S0454, TD-4150P-300, TD-4151M-JA02, TD-4151M-JA500, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix

Gas Standard - A-38, AOC Appendix 616

Gas Standards - A-38, A-38.1, AOC Appendix TD-4412P-07, RMI 04 Excerpts for IDEs, TD-4008P-01 Attachment 4_AOC Document, Gas Map Symbols, TD-4412P-07-JA01d, TD-4412P-07-F01, TD-4412P-07 Attatchment 1, TD-4412P-07-F05, TD-4412P-07-JA02, AOC Appendix, Onboarding course 14.0Pipeline Markers and TD 4412P-09, L-12v4, L-15v2, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix Indicators

08-03.00

Maintain Line Markers

1:1

1 yr

CBT/Exam

Oral

703

08-04.00

Aerial Patrol

1:1

1yr

CBT/Exam

Oral

701

TD-4008P-01 Attachment 4_AOC Document, TD-4412P-07, TD-4412P-07-F10, TD-4412P-07-Attachment 2, TD-4412P-07-JA01, TD-4412P-07-F01, AOC Appendix

09-01.00

Conduct Survey

1:1

1 yr

CBT/Exam

Obs/Oral

702

OQ Basic Plan, TD-4110P-03, TD-4110P-03-F01, TD-4110P-03-JA-01, TD-4110P-08, GS&S M-55, GS&S M-53, GS&S M-54, TD-4110P-09, TD-4110P-13, TD-4110P-21, TD-4110P-22, TD-4110P-25, TD-4110P-23, TD-4110P24, TD-4110S, Gas Symbology, AOC Appendix

09-02.00

Leak Investigation

1:1

1 yr

CBT/Exam

Obs/Oral

651

TD-4110P-09-JA01, TD-4110P-13, TD-4110P-18, TD-4110P-21, TD-4110S, Gas Map Symbols, TD-4008P-01, TD-4110P-03-JA15

09-05.00

Leak Survey - (RMLD)

1:1

1 yr

CBT/Exam

Obs/Oral

723

S4110, RMLD Manual, OQ Basic Plan, TD- 4110P-23, TD-4110P-21, TD-4110P-03, TD-4008P-01 Attachment 4_AOC Document, AOC Appendix

09-09.00

Leak Survey DP-IR (Detecto Pak-Infrared)

1:1

1 yr

CBT/Exam

Obs/Oral

702

TD-4008P-01, TD-4008P-01 Attachment 4_AOC Document, TD-4110P-03, TD-4110P-09, TD-4110P-09-JA01, TD-4110P-21, DPIR User Manual, TD-4110P-03-JA15, TD-4100S, AOC Appendix

10-01.00

Transmission Line Repair Procedures by Welding

1:0

1 yr

CBT/Exam

Obs/Oral

201

10-02.00

Weld Inspection

1:0

1 yr

CBT/Exam

Oral

203

B-23, TD-4160P-20, TD-4160P-60, TD-4160P-61, TD-4160P-62, AOC Appendix

10-04.00

Transmission Line Repairs - Mechanical

1:1

1 yr

CBT/Exam

Obs/Oral

707

Gas Standards – A-60.2, B-53.2, TD-4100P-05, AOC Appendix

10-05.00

Pipe Bending

1:1

1 yr

CBT/Exam

Obs/Oral

PGE 10-05

15-02.00

Monitor Distribution Recording Devices

1:1

1 yr

CBT/Exam

Obs/Oral

602

H-14, TD-4008P-01-Attachment 4, TD-4125P-05, TD-4540P-01, 1823581, 1823582, AOC Appendix

17-01.00

Inspect / Maintain Emergency Valves

1:1

1 yr

CBT/Exam

Obs/Oral

716

Gas Standards – TD-4430B-003, WP4430-04, Gas Bulletin 280, , AOC Appendix

17-03.00

GSO - Manual Valve Operation

1:1

1 yr

CBT/Exam

Obs/Oral

007

WP 4430-04, WP 4430-04 Attachments 4 & 5, WP 4540-01, TD-4100-10, TD 4430B-001, S4460, AOC Appendix, SH&C 232, Symbols Requirements Operating Maps and Diagrams

18-01.00

Inspect Vault

1:1

1 yr

CBT/Exam

Obs/Oral

717

H-14, S4414, S4446, 1823581, 1823582, AOC Appendix

202

616 704

708

Gas Standards - A-60, A-63, A-64, D-30.4, TD-416OP-31, AOC Appendix

A-36 vs 10, Gas Operations PPE Matrix. Field Bending Log

Page 2 of 3

Revision 32, January 04, 2018

Pacific Gas & Electric Company Note: To be qualified on a PG&E task, you must complete the following steps (order is not important): 1) Complete the on-line training and exam(s) for all corresponding Veriforce CCTs and/or PG&E tasks (frequency is based on CCT or PG&E requirements) 2) Be successfully evaluated for all corresponding Veriforce CCTs and/or PG&E tasks (frequency is based on CCT or PG&E requirements) 3) Review and acknowledge understanding of applicable PG&E procedures (annual requirement) 4) Successfully complete the applicable PG&E on-line exam (annual requirement) 5) Review and acknowledge the PG&E AOC Job Aid (annual requirement) 6) Review and acknowledge the PG&E Onboarding Training

PG&E CT # Task Description

21-01.00

00-DW

SOC

Requal Int

Trng Method

Eval Method

CCT(s), Corresponding CCT CBT(s), PG&E task(s), and Corresponding PG&E Task CBT(s)

Polyethylene Pipeline Connection Inspection (Inspectors)

1:0

1 yr

CBT/Exam

Written Exam

PGE21-01

Diamond Wrap

1:0

3 yr

N/A

Oral/Cert

721

Additional PG&E Requirements

Applicable PG&E Procedure(s)

Onboarding course 5.6Distribution and Gas Standards - A-93, A-93 Attachment B, TD-4170P-31, TD-4170P-32, TD-4170P-33, TD-4170P-34, TD-4170P-35, TD-4170P-40, TD-4170M58:M70P-41, TD-4170P-50, TD-4170P-52, TD-4170P-53, M-10.2, M-11.2, TDApplicant Installed 4170S, TD-4170P-57, AOC Appendix Inspection N/A

Page 3 of 3