Construction Progress Report - CMSA

Construction Progress Report April 2008 Wet Weather Improvements Project Central Marin Sanitation Agency...

242 downloads 672 Views 1MB Size
Construction Progress Report April 2008 Wet Weather Improvements Project Central Marin Sanitation Agency

Table of Contents Section 1

Executive Summary

Section 2

Project Photos

Section 3

Logs

Executive Summary Contract Number

07-01

General Contractor

Western Water Constructors

Contract Bid Amount

$35,550,000.00

Change Orders to Date

4

Pending/Anticipated Change orders

7 items

Notice to Proceed

October 8, 2007

Original Contract Time

910 calendar days

Working Days Elapsed

205

Working Days Remaining

705

Milestone 1 (CCT & EPS)

July 29, 2009

Milestone 2 (All other work)

March 6, 2010

Rain days – Accepted to date

7 of 50 included within contract time

Contract Change Order(s) Time Extension

0

Final Completion Date

April 5, 2010

Total Project Time Expended

22.5%

Total Project Cost Expended

29.5%

Work Progress during April 2008 by Area or System: 1. General: Western Water proposed an alternate installation of the 84” x 66” wye at the outfall area. This proposal was reviewed by the Agency and Engineer, who requested additional information and research before acceptance of the proposed installation. (At the beginning of May, Western Water’s research concluded that the proposed alternate installation would not be possible based on the steel cylinder thickness.) Western Water submitted the March 2008 monthly schedule update. No major changes to the project baseline schedule were noted. Western Water (WW) maintained the Storm Water Pollution Prevention Plan best management practices (BMPs). Western Water has submitted rain event inspection forms for the project files. Western Water continues routine weekly safety tailgate meetings, weekly safety checks, as well as the monthly safety audit performed by WW’s safety officer. Written reports of all meetings, checks and safety audits have been submitted for the record.

2. Polymer Facility: Western Water continued the installation of the new polymer lines, 3-water and 1-water lines from the west side of the plant road to the pipe sleeves in the structure walls and encased the new pipes in controlled low strength material (CLSM).

Western Water and their electrical subcontractor, Aspen Timco, continued trenching and installing the electrical duct bank from the polymer facility to the CMSA Administration Building following the alternate routing plan, approved in Change Order No. 003. The pull box remains to be installed in this area; the duct bank has been encased with red concrete and backfilled, and conduits have been installed into the Administration Building.

3. Gallery A & B Improvements, including Grit Chamber 3 and Headworks Western Water rerouted the fire water piping, channel air and Ross Valley Pre-chlorination lines in Gallery A in preparation for the primary influent channel connection and other demolition work. Western Water installed a portion of the grit pump piping. Western Water demolished the parapet wall at the south end of Gallery A/B. They also cut out the wall below the parapet for the influent channel connection and covered the opening with framed plywood for the interim until further work is completed in this area. Western Water set the Aeration Blower in place in the blower room and installed the piping for the plant air to be connected to the aeration blower.

4. Primary Clarifiers 6 & 7 Subcontractor Stroer & Graff began installing the Type 1 shoring (soldier beam and lagging) for the primary clarifiers. Soldier beams were installed in the area, but have not crossed the current plant road yet.

5. Chlorine Contact Tanks (CCT) 5 & 6 Western Water completed the excavation and backfill with CLSM by mid-April. Western Water placed and compacted 6-inches of aggregate base in preparation for forming the slabon-grade for the CCT. Subcontractor Condon-Johnson began installation of the six drilled concrete piers which will support the new influent channel from the existing chlorine contact tanks to the new tanks.

6. Effluent Pump Station (EPS) After completing the excavation and backfill as noted above for the CCT, Western Water began forming for the slab-on-grade. They also formed and placed the concrete for the drain sump slab-on-grade.

7. Secant Retaining Wall and other Site improvements Subcontractor Condon Johnson completed the secant pile retaining wall with the float finish of the Shotcrete face. Western Water installed forms, placed and compacted aggregate base material and tied reinforcing steel for the v-ditch behind the secant pile retaining wall. Western Water began constructing a temporary access road where the new road will be permanently installed. The Ross Valley Interceptor pipe under this new road location is not encased as it is under the current road. Carollo Engineers is working on a design to protect the pipe under the new road. Western Water will either avoid crossing the Ross Valley Interceptor in the new road or will only run empty trucks over that area until the new design is received and installed over the pipe.

8. Aeration Tanks Aspen Timco, electrical subcontractor, continued installation of conduits on the aeration tank control building. This work will continue in the month of May and connections made during scheduled maintenance shutdowns of the tanks.

9. Review Item Summary Please see attached open RFI and Submittal logs in Section 3 for details of the following outstanding items.

Review Items

Total Received to Date

RFIs Submittals Certified Payroll

67 231 141

Number Received in April 12 48 25

Number Returned / Reviewed in April 9 34 25

10. Change Order Summary Approved Change Orders Contract Change Order No. 001 Contract Change Order No. 002

Description

Cost

One-time relocation of PG&E gas Line

$0.00

Miscellaneous Small Changes (9 items)

$1,043.00

Contract Change Order No. 003

Electrical/Instrumentation Conduit Routing to Administration Building - $0.00 Additional 3W Service at Polymer Truck Pad - $5,332.00 Shotcrete Finish at Secant Pile Retaining Wall - $21,500.00 Grit Blower Piping - Stainless Steel vs. Carbon - $6,371.00 Rerouting polymer lines at Headworks deck – ($1,000.00) Manhole at Eastern Drainage Ditch Infill - $7,200.00 Slab extension on north side of Polymer Facility - $1,000.00 Pipe Ts in lieu of pipe saddles in Galleries - $0.00

Negotiated $40,403

Contract Change Order No. 004

Secant pile retaining wall additional work over Ross Valley Interceptor per Design Clarification No. 002, performed on time and material.

Pending $54,228.23

Pending Change Orders

Contract Change Order No. 005

Description

1) Electrical Grounding System – shown on drawings to connect to steel beams at three structures which do not have steel beams. 2) Reroute scum drain at primary clarifiers 6 & 7 Western Water proposed alternate routing of the scum drain at clarifiers 6 & 7 to reduce the number of turns in the pipe

Cost

Pending Cost to be determined

3) 4) 5) 6) 7)

Value Engineering Items

run. This was reviewed and accepted by the Engineer and Agency. Increase length of new flare deck to match existing pad dimension. Personnel gate in fence on secant pile retaining wall Additional 40 linear feet of fence for fall protection on secant pile retaining wall. Credit to change copper plates to stainless steel at secant pile retaining wall. Credit to delete factory witness test requirement for Grit Classifier

a) Excavation and Shoring Changes at Chlorine Contact Tank Area: Western Water proposed an alternate method to excavate and place the controlled low strength material in the chlorine contact tank area. This method was accepted by the Agency. The cost savings of this method will be shared by the Agency and Western Water.

Pending Savings to be determined

10. Apprentices Three apprentices worked on the project throughout the month of April, two electrical apprentices and one general laborer.

Work Activities planned for May 2008: • • • • • • • • • • • • •

Complete installation of soldier beam and lagging shoring with tie backs at the primary clarifier area Begin excavation at the primary clarifier area Continue forming and reinforcing steel installation at Chlorine Contact Basin and Effluent Pump Station. Begin concrete placement of slab and wall sections at the effluent pump station and chlorine contact tanks Complete v-ditch behind the secant pile retaining wall. Install fence along top of secant pile retaining wall Complete installation of the electrical duct bank around Primary Clarifiers 6 and 7 Complete installation of electrical duct bank and temporary power from Switchgear Building to the effluent pump station. Complete installation of grated trench drain Complete installation of electrical duct bank from new polymer facility to the existing administration building. Continue installation of exposed electrical conduit at existing aeration tanks Continuation of Storm Water Pollution Prevention Plan Submittals provided for review, including schedule update.

Wet Weather Improvements April 2008 Photos taken 04.30.2008

Progress Photo 01 - Overview of Outfall Area

Progress Photo 02 – Effluent Pump Station and Chlorine Contact Tank Area backfilled for formwork.

Wet Weather Improvements April 2008 Photos taken 04.30.2008

Progress Photo 03 – Chlorine Contact Tank & Effluent Pump Station Area backfilled and compacted.

Progress Photo 4 – View East from Solids Handling Building

Wet Weather Improvements April 2008 Photos taken 04.30.2008

Progress Photo 05 – View West from Solids Handling Building; Secant Pile Retaining Wall, Grated Trench Drain and Primary Clarifier Shoring

Progress Photo 06 – View East from Headworks Building; Secant Pile Retaining Wall and Primary Clarifier Shoring

Wet Weather Improvements April 2008 Photos taken 04.30.2008

Progress Photo 07 – Grated Trench Drain east of switchgear building, in front of secant pile retaining wall

Progress Photo 08 – V-Ditch formed and reinforcing steel placed behind Secant Pile Retaining wall

Wet Weather Improvements April 2008 Photos taken 04.30.2008

Progress Photo 09 – Demolition and removal of Parapet and wall at south end of Gallery A.

Progress Photo 10 – Placed Concrete for Drilled Concrete Piers at Chlorine Contact Tank.

Wet Weather Improvements April 2008 Photos taken 04.30.2008

Progress Photo 11 – Backfill to Polymer Facility north side.

Progress Photo 12 – Electrical conduits entering Administration Building from Polymer Facility.

Central Marin Sanitation Agency CMSA - Wet Weather Improvement

Open Requests for Information

07-01 Project No: 061-0491.01 Job No:

RFI Number From 00039

To

WESTWATR HARRIS

Title CCT 1-4 Modifications 16-Inch 3W

Change Issue

Status Request OPN

Date: 4/30/2008 1 of 1 Page: Dated

On sheet M-9.5 of the drawings typical detail S200 notes 1/31/2008 that concrete will be chipped and hammered out an oversized hole in order to recover existing rebar and place and grout a wall spool for the 16 inch 3 water pipe line to pass through the existing Chorine Contact Tank Walls.

Responded

Required 2/6/2008

We propose to core drill a 20 inch hole for the 16 inch pipe. For each of the three interior walls we propose to use 1 link seal grouted in on both sides with 10,000 lbs grout. For each of the two exterior walls we propose to use 2 link seals grouted in on both sides and between using 10,000lbs grout. This is our recommendation. Thank you 00061

WESTWATR HARRIS

PG&E Pull Box

OPN

4/15/2008 The PG&E box at the north end of the plant is sitting approx. 1’ to 2’ lower than Grade. The PG&E inspector said that an extension ring was necessary to bring the box to grade. As this was not in the bid documents, it will be additional work. If this work is required, ATI will proceed upon approval of Change Order. Verify requirement and approve Change Order, if necessary.

4/22/2008

00065

WESTWATR HARRIS

Conduit Penetration at Switchgear

OPN

Per the above mentioned drawings, we are to provide a 4/29/2008 thru-wall seal when penetrating the wall. As the conduit will be stubbing out of the back of the pull box, we do not know how the seal will work. Please provide a detail showing the use of thru-wall seal, when used coming out of a pull box.

4/30/2008

Report r_a_rfi_03_harris

Central Marin Sanitation Agency CMSA - Wet Weather Improvement

Open Submittal Log - Sorted by Submittal No. Job No:

07-01

Date: 4/30/2008 1 of 2 Page:

Project No: 061-0491.01 Rev. Title

Status

193

02810-1.04

02810

001

Underground Sprinkler System

R&R

3/6/2008

3/7/2008

3/18/2008

3/21/2008

WESTWATR

161

03200-1.05-CCT 03200

002

Chlorine Contact Tank Rebar

R&R

4/1/2008

4/4/2008

4/14/2008

4/15/2008

WESTWATR

192

05500-1.03-A.2

05500

Access Hatch for Valve Vault

R&R

3/4/2008

3/6/2008

3/24/2008

3/25/2008

WESTWATR

220

07510-001

07510

001

Roofing Product Data

OPN

4/8/2008

4/11/2008

CAROLLO

221

07510-002

07510

001

Roofing - Samples

OPN

4/8/2008

4/11/2008

CAROLLO

217

07510-003

07510

Roofing - Installation Instructions

OPN

4/8/2008

4/11/2008

CAROLLO

217

07510-004

07510

Roofing - UL & FM Certificates

OPN

4/8/2008

4/11/2008

CAROLLO

217

07510-005

07510

Roofing - Warranty

OPN

4/8/2008

4/11/2008

183

11293-1.04

11293

Fabricated Slide Gates

R&R

3/18/2008 3/18/2008

3/27/2008

3/28/2008

WESTWATR

183

11294-1.05 A-E

11294

Cast Iron Sluice Gates

R&R

3/18/2008 3/18/2008

3/27/2008

4/1/2008

WESTWATR

228

11312D-1.05A

11312D

Vertical Propeller Pumps

OPN

4/24/2008 4/24/2008

118

11312F-1.05-A

11312F

001

GromanRupp Model T6A3S-B Pump

R&R

12/18/2007 12/18/2007

1/9/2008

1/10/2008

WESTWATR

118

11312F-1.11.B

11312F

001

Spare Parts List

R&R

12/18/2007 12/18/2007

1/9/2008

1/10/2008

WESTWATR

118

11312F-2.11.B

11312F

001

US Motors Model H15P3B

R&R

12/18/2007 12/18/2007

1/9/2008

1/10/2008

WESTWATR

150

11312I-1.05

11312I

002

Progressing Cavity Pumps

OPN

4/29/2008 4/30/2008

210

11312J-2.01-B1

11312J

001

Submersible Sump Pump

R&R

3/20/2008 3/21/2008

4/17/2008

4/18/2008

WESTWATR

131

11312K-1.05

11312K

002

Submersible Sump Pumps (EPS)

R&R

2/14/2008 2/14/2008

2/25/2008

2/29/2008

WESTWATR

162

11312O-1.05A

11312O

002

Horizontal End Suction Pump w/O&M

OPN

4/29/2008 4/30/2008

229

11318-1.04A,B,G 11318

001

Diesel Engine Drive System

OPN

4/24/2008 4/24/2008

212

11343-1.04 B-D

11343

Helical Scum Skimmers

R&R

3/27/2008 3/31/2008

4/28/2008

4/29/2008

WESTWATR

189

11351-001

11351

001

1.04-A Product Data

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

189

11351-002

11351

001

1.04-B Shop Dwgs. & Calculations

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

189

11351-003

11351

001

1.04-C Manufacturer's Dwgs

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

189

11351-004

11351

001

1.04-D.2 Manufacturer's Instruct.

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

189

11351-005

11351

001

1.05-A.2 List of Installations

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

189

11351-006

11351

001

1.08 Warranty

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

189

11351-007

11351

001

1.09-B.2 Spare Parts List

R&R

3/4/2008

3/6/2008

4/3/2008

4/7/2008

WESTWATR

002OM

11376-1.05-F

11376

001

Aeration Blowers - O&M

R&R

2/12/2008 2/13/2008

2/20/2008

2/25/2008

WESTWATR

114

11378-1.05-D

11378

002

Coarse Bubble Aeration System - O&M

OPN

2/27/2008 2/27/2008

220

12347-1.02-A&B

12347

001

Lab Casework, Sink, & Fixture

OPN

4/15/2008 4/16/2008

117

13120-1.03-A

13120

002

FRP Launders

R&R

2/19/2008 2/19/2008

3/24/2008

4/1/2008

WESTWATR

117

13120-1.03-A 1

13120

002

FRP Launders - Drawing B10

R&R

2/19/2008 2/19/2008

3/24/2008

4/1/2008

WESTWATR

117

13120-1.03-A2

13120

002

FRP Launders - Drawing B11

R&R

2/19/2008 2/19/2008

3/24/2008

4/1/2008

WESTWATR

117

13120-1.03-A3

13120

002

FRP Launders - Drawing B12

R&R

2/19/2008 2/19/2008

3/24/2008

4/1/2008

WESTWATR

117

13120-1.03-A4

13120

002

FRP Launders - Drawing B13

R&R

2/19/2008 2/19/2008

3/24/2008

4/1/2008

WESTWATR

163

13209-1.04

13209

001

Above Ground Fuel Storage Tank

R&R

1/29/2008 1/30/2008

3/31/2008

3/31/2008

WESTWATR

166

13422-2.01

13422

001

Rotameter Flow Field Instrument

R&R

1/31/2008 2/1/2008

2/13/2008

2/15/2008

WESTWATR

213

13422-2.01 & 2

13422

001

Rotameter Type Flowmeter

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

WESTWATR

213

13422-2.02

13422

001

Thermal Flow Switches

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

WESTWATR

213

13422-2.03 & 4

13422

001

Magnetic Flow Meter

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

WESTWATR

213

13422-2.06

13422

001

Water Flow Switches

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

WESTWATR

213

13423-2.01

13423

001

Float Type Level Switches

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

WESTWATR

213

13424-2.01

13424

001

Pressure Switches

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

WESTWATR

183

13445-1.04

13445

002

Hydraulic Cylinder Operators

R&R

3/18/2008 3/18/2008

3/27/2008

4/1/2008

WESTWATR

183

13446-1.03

13446

002

Valve & Gate Operators

R&R

3/18/2008 3/18/2008

3/27/2008

4/1/2008

WESTWATR

199

13452-1.02-A

13452

001

RTU and Distributed I/O System

OPN

3/18/2008 3/19/2008

4/17/2008

199

13453-1.03-A

13453

001

HMI & SCADA System - Product Data

OPN

3/18/2008 3/19/2008

4/17/2008

173

14624-1.04-A&B

14624

Monorail Hoist & Trolley System

R&R

2/1/2008

3/24/2008

3/25/2008

034

15112-1.04A-C.1 15112

003

Butterfly Valves

OPN

4/29/2008 4/30/2008

213

15120-2.09

001

Pressure Gauges

R&R

3/27/2008 3/31/2008

4/23/2008

4/24/2008

15120

2/4/2008

Forward

Required Finish

Package

002

Rcvd.

Latest Dates Sent Return

Item No. Submittal

BIC

CAROLLO

CAROLLO

CAROLLO

CAROLLO CAROLLO

CAROLLO CAROLLO

HARRIS HARRIS WESTWATR CAROLLO WESTWATR Report r_sb_01_c_01

Central Marin Sanitation Agency CMSA - Wet Weather Improvement

Open Submittal Log - Sorted by Submittal No. Job No:

07-01

Date: 4/30/2008 2 of 2 Page:

Project No: 061-0491.01 Rcvd.

Latest Dates Sent Return

Package

Rev. Title

Status

145

15772-001

15772

001

Heat Tracing Cable

R&R

1/3/2008

1/4/2008

218

15812-1.04 A&B

15812

001

Metal Ductwork

OPN

4/3/2008

4/11/2008

CAROLLO

224

15814-1.03-B

15814

001

FRP Ductwork Shop Drawings

OPN

4/17/2008 4/18/2008

CAROLLO

129

15830-2.01

15830

002

Type 1, Down Blast Centrifugal Roof

NEW

4/17/2008 4/18/2008

CAROLLO

129

15830-2.02

15830

002

Type 2, Up-Blast Centrifugal Roof

OPN

4/17/2008 4/18/2008

CAROLLO

129

15830-2.03

15830

002

Type 3, In Duct Fan

OPN

4/17/2008 4/18/2008

CAROLLO

225

15852-1.04-A

15852

001

Louver - Shop Drawings

OPN

4/17/2008 4/18/2008

CAROLLO

226

15855-1.04-A

15855

001

Air Handling Units - Shop Drawings

OPN

4/17/2008 4/18/2008

CAROLLO

149

16123-001

16123

003

Type TC Wire- 2.02.A&B

OPN

4/22/2008 4/24/2008

CAROLLO

149

16123-002

16123

003

Typw TC Inst. Cable - 2.03.A&B

OPN

4/22/2008 4/24/2008

CAROLLO

149

16123-003

16123

003

Terminal Products

OPN

4/22/2008 4/24/2008

CAROLLO

149

16123-004

16123

003

Cable Pulling Lubricant - 2.06.C

OPN

4/22/2008 4/24/2008

CAROLLO

149

16123-005

16123

003

Noalox Anti-Oxident Compound

OPN

4/22/2008 4/24/2008

CAROLLO

223

16133-Details

16133

001

Conduit Layout E-4.18 - E-4.21

OPN

4/17/2008 4/18/2008

CAROLLO

222

16133-Prim. Cl.

16133

001

Primary Clarifier Conduit Layout

OPN

4/17/2008 4/18/2008

CAROLLO

149

16134-005

16134

003

SS 4X Enclosures - 2.05.A

OPN

4/22/2008 4/24/2008

CAROLLO

149

16140-009

16140

003

Al Control Enclosures - 2.08.D

OPN

4/22/2008 4/24/2008

CAROLLO

149

16140-010

16140

003

Pilot Devices - 2.09

OPN

4/22/2008 4/24/2008

201

16144-1.02-A

16144

001

Disconnect Switches

R&R

3/12/2008 3/13/2008

4/1/2008

4/3/2008

WESTWATR

200

16273-1.03-A

16273

001

Low Voltage Distribution Transform

R&R

3/12/2008 3/13/2008

4/1/2008

4/3/2008

WESTWATR

231

16342-1.04-A

16342

001

600V Motor Control Center - Shp Dwg

OPN

4/29/2008 4/30/2008

CAROLLO

203

16416-1.03-B

16416

001

Transient Voltage Surge Suppressors

OPN

4/17/2008 4/17/2008

CAROLLO

204

16448-1.04-A

16448

001

Panelboards - Product Data

OPN

4/17/2008 4/17/2008

CAROLLO

230

16500-1.03-A

16500

001

Lighting - Product Data w/Seismic

OPN

4/29/2008 4/30/2008

CAROLLO

230

16500-1.03-B

16500

001

Lighting - Finish Sample

OPN

4/29/2008 4/30/2008

CAROLLO

1/17/2008

Forward

Required Finish

Item No. Submittal

1/18/2008

BIC WESTWATR

CAROLLO

Report r_sb_01_c_01