specifications and standards - NHAI

1. Manual of Specifications and Standards to apply. Subject to the provisions of Paragraph 2 of this Annex-I, Two-Laning of the Project. Highway shall...

8 downloads 949 Views 12KB Size
NHAI

Technical Schedules

SCHEDULE – D (See Clause 2.1)

SPECIFICATIONS AND STANDARDS 1

Two-Laning The Concessionaire shall comply with the Specifications and Standards set forth in Annex-I of this Schedule-D for construction of the Two-Lane Project Highway.

Two laning of Dindigul-Theni section km 2.750 to 73.400 of NH-45(EXtn.) and Theni-Kumili section from km 215.500 to 273.600 of NH-220 in the state of Tamil Nadu ON DBFOT (Annuity) Basis Project

D-1

NHAI

Technical Schedules

Annex - I (Schedule-D)

Specifications and Standards for Two-Laning 1

Manual of Specifications and Standards to apply Subject to the provisions of Paragraph 2 of this Annex-I, Two-Laning of the Project Highway shall conform to the Manual of Specifications and Standards for DBFOT Road Projects published by the Indian road Congress (IRC No. IRC:SP:73-2007). (An authenticated copy of the Manual has been provided to the Concessionaire as part of the bid documents.)

2

Deviations from the Manual Notwithstanding anything to the contrary contained in the aforesaid Manual, the following Specifications and Standards shall apply to the Two-Lane Project Highway, and for purposes of this Agreement, the aforesaid Manual shall be deemed to be amended to the extent set forth below: S. No.

Clause

1

2.1(ii)a

2

2.5

3

7.1 (ii) & (vii)

4

Section 10 Toll Plazas

5

Add new clause

Description

Deviation

Carriage-way width in Carriageway width in Built up Areas shall be as specified in Built up Areas Schedule B (Ref. Description of cross sections) Width of the shoulders is Width of earthen (granular) shoulder shall be 1.00 m and paved 2.5 m on either side shoulder shall be 1.5m on either side throughout the project stretch except for the ghat section (existing chainage from 215+500 to 222+400 on NH 220). In case of Ghat section, it is as given in Schedule ‘B’. Width of Bridge at deck The width of the bridge at deck level shall be as specified in level Schedule ‘B’. Scope does not include provision of Scope fee collection staff. Rain Water Harvesting Rain Water Harvesting Structures shall be designed and provided as structures per the guide lines of MoEF and State Environmental Department.

Two laning of Dindigul-Theni section km 2.750 to 73.400 of NH-45(EXtn.) and Theni-Kumili section from km 215.500 to 273.600 of NH-220 in the state of Tamil Nadu ON DBFOT (Annuity) Basis Project

D-2